Tag: HFR to ALTO

  • The wrong answer to the right question

    Coalition for Better Rail · ALTO HSR Citizen Research Initiative · The HPR Research Report

    The Wrong Answer to the Right Question

    The corridor genuinely needs better trains. What it got instead was a project that grew far beyond its original plan during procurement — and that can’t be fixed with tweaks, because its problems come from how it was chosen, not how it’s being built.

    This chapter doesn’t dispute that the Windsor–Toronto–Ottawa–Montréal corridor needs better intercity rail. It does. What it disputes is ALTO — on grounds that are about method and evidence, not politics. We trace how a modest upgrade of a largely existing, disused rail corridor turned into a 300 km/h greenfield megaproject during a competitive bidding process, lay out four structural problems with the project as designed, and explain why none of it can be patched from the inside.

    Source Note

    Much of this chapter draws on documents obtained through Access to Information requests — internal board and executive records, procurement files, and the independent fairness monitor’s final report — along with the Initiative’s own independent cost, ridership, and route-friction models. Specific releases are cited by their file numbers throughout. Some key documents, including the internal slide where the project’s scope was reframed, remain withheld.

    Download
    Chapter 2: The Wrong Answer to the Right Question (PDF)
    The full chapter, with footnotes and sourcing
    Download PDF
    2.1 · The Real Problem

    The corridor genuinely needs better trains

    The Windsor–Toronto–Ottawa–Montréal corridor connects Canada’s two largest metro areas and the national capital, and generates roughly half the country’s GDP. Despite that, intercity rail service on it is among the worst in any comparable wealthy country. VIA Rail shares track with CN freight, and freight trains get priority — when both need the same stretch of track, the passenger train waits in a siding. The result is slow, unreliable, and infrequent service.

    <64%
    VIA Rail’s on-time performance in 2023 — worse than Air Canada’s 63%, which itself ranked last among North America’s ten largest airlines
    4h+
    Scheduled Toronto–Montréal journey time — more than double a competitive flight, including check-in
    ~50%
    Share of Canada’s GDP generated in this corridor — the economic weight today’s rail service fails to serve

    Schedules are padded with hours of slack to absorb the delays that freight priority makes routine. The result isn’t competitive with driving or flying, and VIA can’t simply add more trains without bumping freight that has the contractual and legal right of way. So the question this report asks isn’t whether the corridor needs investment. It’s what kind of investment actually delivers it — at what cost, on what timeline, with what risk.

    2.2 · How This Happened

    A modest upgrade grew into a much bigger, much pricier project — during the bidding process

    ALTO’s cost and ambition problems didn’t come from ordinary planning drift. Records obtained through Access to Information show the project’s scope escalating in the middle of the bidding process itself — not through any public announcement or debate. Understanding how that happened explains why ALTO costs what it costs today.

    One thing to be clear about up front: this is not a claim that the procurement was run improperly. BDO Canada, the independent fairness monitor appointed in 2022, concluded in its final report of May 2025 that the process it observed was carried out in a fair, open and transparent manner, and recorded no fairness concerns at any stage. The problem is not that rules were broken. It is that a process run properly within its own terms produced a project no one had put to Parliament.

    What was on the table originally

    The project ALTO replaced was VIA Rail’s High Frequency Rail (HFR) plan: a dedicated-track plan running at up to 177 km/h, largely reviving a long-disused rail right-of-way through Peterborough, Havelock, and Smiths Falls — a separate, more direct route away from the CN Kingston Subdivision VIA still shares with freight today — delivered incrementally, segment by segment. Its own 2021 business case projected about 13.5 million riders a year, at a capital cost roughly a quarter to a third of what ALTO now proposes. That’s the baseline the public was never shown as a discrete choice against what came next.

    An open-ended bidding process

    The request for proposals went out in October 2023 without a settled route — internal records show the route was still being debated at the executive and board level as late as March 2024, five months after bidding opened. It also asked every bidder for two designs: one topping out at 200 km/h, and a second, more ambitious one with high-speed sections. The process then included 36 structured private meetings between the government and each bidder over eight and a half months.

    All three bidders proposed something bigger

    A Privy Council Office briefing note of 20 February 2025, released under access to information, records that as the bidding progressed all three shortlisted consortia put forward designs more ambitious than the high-frequency plan — new routes on largely new land, above 250 km/h. The jump in scope did not come from any one bidder. The winning consortium, Cadence — CDPQ Infra, AtkinsRéalis, Keolis, SYSTRA Canada, SNCF Voyageurs, and Air Canada — brings substantial experience in dedicated, higher-speed rail: its members built Montréal’s REM and operate France’s TGV network. What has never been published is the comparison the bidding process was set up to produce. The same briefing note credits an unnamed third party with concluding those bigger proposals would deliver greater benefits, and that analysis has not appeared in any release to date.

    Billions committed before the plan was finished

    The government committed $3.9 billion in the 2024 Fall Economic Statement before the business case was finalized and before a route was chosen. The internal slide that appears to document the scope escalation — titled “Level of Ambition Supported by Business Case” — remains withheld from public release. Once the funding commitment was public, there was effectively no way back to the smaller project.

    Selling the bigger, pricier version

    With the scope already locked in, the government faced a communications problem: a project that started as “VIA HFR” was now something much closer to European-style high-speed rail. Internal records show “high frequency” tested poorly with Ontario audiences, while the name “Alto” tested well with 18–34-year-olds and worked bilingually. A national ad campaign promoting the project’s benefits ran while the business case and route documents were still being withheld from information requesters.

    The pattern, stated plainly

    A project that entered the bidding process as a $9–12 billion, 177 km/h upgrade of a largely disused rail corridor came out the other side as a $60–90 billion (on the government’s own published figures — our independent estimate is materially higher), 300 km/h greenfield railway. That change in scope was never put to Parliament or the public as a choice. It emerged from the mechanics of the procurement itself.

    2.3 · Four Problems Built Into the Design

    Route, math, price tag, ridership — each one falls short

    Having won a mandate for a much bigger project than the one that went to bid, ALTO’s proponents faced four separate problems: a route through sensitive land, a business case that has to clear a federal investment bar, a cost estimate that has to hold up, and a ridership forecast that has to be believable. None of the four holds up well under independent scrutiny.

    2.3.1 · The route runs through some of the most sensitive land in the corridor

    ALTO’s proposed new corridor crosses the Frontenac Arch Biosphere Reserve — a UNESCO-designated ecological corridor — the Napanee Limestone Plain, habitat for several species at risk, and Leda clay deposits south of Ottawa with known engineering hazards at high speed. This wasn’t a routing choice made for technical reasons; it reflects a decision to build an entirely new, 300 km/h-optimized corridor rather than follow existing, already-disturbed infrastructure. In our Participant Experience Survey, only 2% of respondents received direct notification about ALTO, and 88% found the information they did get inadequate. Our Community Friction Index — which scores corridors on land conflict, municipal pushback, expropriation exposure, ecological sensitivity, and public mobilisation — puts ALTO’s corridor at 54 out of 100, in the high-friction range. That matters financially, not just politically: in our statistical model, community friction is a significant predictor of cost overruns.

    2.3.2 · The math doesn’t clear the government’s own bar

    The only published economic appraisal of this corridor is the December 2021 business case for the predecessor project. It puts the benefit-cost ratio at about 0.13 over a 30-year period — about thirteen cents of measured value for every dollar spent — rising to about 0.4 once two newer and less established benefit categories are added in. A separate calculation in the same document shows a net loss of $21.1 billion in present-value terms. These are the government’s own figures. A ratio of 1.0 is simply break-even, the point where benefits equal costs. Our independent analysis, which grounds every input in how comparable projects have actually performed rather than project-specific projections, finds the ratio is likely far worse still.

    ScenarioWhat it shows
    Published (Dec 2021 appraisal)
    30-year evaluation period
    Benefit-cost ratio ~0.13, or ~0.40 on the expanded basis
    Initiative reference-class estimate
    Cost assumed: ~$143B
    Benefit-cost ratio ~0.03–0.11
    Break-evenBenefit-cost ratio of 1.0 — benefits equal costs
    In plain terms

    ALTO fails its own government’s investment test on the government’s own numbers. Checking those numbers against how similar projects have actually performed makes the gap worse, not better.

    2.3.3 · The price tag is very likely too low

    ALTO’s published cost range of $60–90 billion comes from an early-stage estimate — the type quantity surveyors flag as accurate only to within roughly ±50%, which makes it a planning figure, not a firm commitment. Our own cost model, built from 16 comparable rail megaprojects worldwide and calibrated to those projects’ actual outcomes, puts ALTO’s realistic central cost at around $143 billion, with a worst-case scenario approaching $200 billion or more once cold-climate engineering risk (frost-susceptible clay, karst terrain, freeze-thaw cycles at high-speed tolerances) is factored in.

    2.3.4 · No independent study backs the ridership numbers

    ALTO projects 24 million riders a year by 2055. No car-dependent North American corridor without existing high-speed rail has ever come close to that. Research on transportation megaprojects generally finds ridership forecasts overstate actual results by about 51% on average. Our own bottom-up model — built from corridor population, trip-making patterns, and VIA’s own ridership data, tested under three different fare and subsidy scenarios — puts 2055 ridership at 3.7 to 17.2 million, with 9.2 million as the central estimate. ALTO’s 24-million target sits 40% above even our upper bound.

    Source2055 ridership estimate
    ALTO’s public target24 million
    ALTO’s internal Corporate Plan figure (by 2059)17 million — about 30% below the public figure
    McGill TRAM stated-preference study~19.7 million (year 50)
    Munk School (U of T) model18–19 million (year 30)
    Standard bias correction applied to ALTO’s own figure8.4 million
    Initiative bottom-up model, central case9.2 million (range: 3.7–17.2 million)
    The pattern here too

    Every independent forecast built from a published methodology lands within or close to our range. ALTO’s own public target is the outlier — and it’s the one figure whose methodology has never been disclosed.

    2.4 · Why Patching It Won’t Work

    These aren’t execution problems — they’re the project’s founding choices

    A different route doesn’t fix the business case. A revised ridership forecast doesn’t fix the cost problem. Tighter project management doesn’t undo the fact that funding was committed before the business case was finished, on a specification set by the bidding process rather than by public need. Four reasons why this can’t be corrected from within:

    It’s been treated as one-of-a-kind, so nothing gets checked against it

    ALTO’s documentation consistently describes the corridor as having no real comparator, which is exactly the reasoning pattern researchers have found opens the door to over-optimistic numbers. Every genuinely comparable project elsewhere in the world gets waved away as not relevant — leaving the project’s own estimate as the only “evidence” available.

    The most optimistic version of the numbers is the one that won

    In competitive funding processes, the most optimistic projection tends to win, because optimism produces a better-looking business case than realism does. A version built on our reference-class numbers — a benefit-cost ratio of 0.03–0.11 — could never have survived the funding decision. The optimistic version did, but only because the more realistic numbers weren’t available yet when the commitment was made.

    The first segment is too weak to stand alone — which is exactly the point

    The planned first segment, Ottawa–Montréal, is the corridor’s weakest market: roughly 98% of that travel is currently by road, and there’s barely any competing flight traffic for a speed premium to beat. It can’t pay for itself. Its economics only work if the network keeps extending toward Toronto — which locks in a public commitment to the rest of the corridor before its full price has ever been disclosed. Britain’s HS2 project shows how badly this can go if it doesn’t: two legs cancelled, leaving a line more than double its original budget serving less than half the original network. HS2 at least stranded into its strongest market. If ALTO’s later phases stall, it strands into its weakest.

    The alternative is quietly being closed off while this proceeds

    The report’s proposed alternative, HPR, would run alongside the existing Highway 401 corridor. Ontario’s ongoing 401 widening is already consuming the road margin that alternative would need, section by section. Every year ALTO’s planning phase continues is a year in which that door narrows further — a real cost that doesn’t show up in any of ALTO’s published figures.

    What’s Next

    What’s in the rest of this report

    This chapter has traced one argument in four parts: the corridor’s need is real (2.1); a modest upgrade became a much bigger project during procurement (2.2); the resulting project has four structural problems (2.3); and none of it can be fixed by refinement (2.4). The chapters that follow set out the alternative.

    Ch. 3
    The HPR alternative. How a passenger line built along the existing Highway 401 and rail corridor can free up freight capacity at the same time, instead of building an entirely new line elsewhere and leaving the freight problem untouched.
    Ch. 4
    Route and cost. Where the line would go and what it would cost, using the same cost model applied consistently to both ALTO and HPR.
    Ch. 5
    Environment and communities. How the two options compare on carbon emissions and disruption to the communities along the route.
    Ch. 6
    How many people would ride it. Ridership estimates built on the real-world pattern, checked four different ways.
    Ch. 7
    Running costs. The ongoing yearly balance between what it costs to operate and maintain the railway, and what fares plus any subsidy bring in.
    Ch. 8
    Is it worth it. A full cost-benefit and financial analysis across a range of scenarios, including the value of the freed-up freight capacity.
    Ch. 9
    Getting it built. How to phase construction, manage the risk of cost overruns, and keep the project accountable to the numbers in this report.
  • Reading Lovegrove

    Reading Lovegrove

    What the UK Cabinet Office’s review of the HS2 Civil Service failures tells us about ALTO.

    ⚠ New UK Cabinet Office Review Published

    In May 2026 the UK Cabinet Office published a review by Sir Stephen Lovegrove — former National Security Adviser and former Permanent Secretary of the Ministry of Defence — into how the British Civil Service failed to identify and act on the deterioration of HS2 before its costs reached £82.2 billion for the London–Birmingham section alone. The review is short, unusually candid, and addresses the institutional architecture Canada is now using to deliver ALTO. gov.uk

    The Lovegrove Review is not about why HS2 went wrong as an engineering project. Its purpose is to explain how a senior G7 civil service, with all the oversight tools a Westminster-system government has, failed to see the disaster coming. That makes it directly relevant to the question Canadians need to ask about ALTO.

    Critical Finding

    The Lovegrove Review documents a four-fold real-terms increase in HS2 Phase 1 costs between 2012 and 2026 — from £20.5 billion to £82.2 billion in constant 2019 prices — on a 225-kilometre stretch of railway. A directly parallel Canadian cost-escalation trajectory has already occurred on the corridor ALTO now proposes to serve: from under C$5 billion for the abandoned High Frequency Rail option in 2016 to C$80–120 billion for ALTO as confirmed in February 2025, a sixteen-to-twenty-four-fold increase within a decade.

    Three Lovegrove findings translate directly to ALTO. First, the corporate form of an arm’s-length delivery body funded entirely from the public purse — HS2 Ltd in the UK, ALTO HSR Inc. in Canada — is, in Lovegrove’s words, “fundamentally ill-suited to this type of arrangement” because the commercial disciplines the corporate form is supposed to deliver do not flow from grant-in-aid funding alone. Second, HS2 Ltd’s board and executive developed a “fortress mentality,” becoming cheerleaders for high-speed rail rather than rigorous delivery managers — a pattern the CRI has been documenting in ALTO’s recent public outputs. Third, and most directly applicable: external reviews must not substitute for official advice on alternative ways of delivering a project before a Final Investment Decision.

    The Lovegrove Review also contains an unusually explicit vindication of dissenting analysis. Lord Berkeley’s January 2020 dissent from the Oakervee panel was dismissed at the time as methodologically unsound. Six years later, the Cabinet Office writes that the thrust of his judgements has proved correct and his estimates closer to today’s outturn than those on which ministers gave the go-ahead. This is the most authoritative G7 government statement to date on the credibility of structured citizen reference-class analysis in high-speed rail governance.

    Download
    Reading Lovegrove — Full Brief (PDF)
    Detailed analysis of the Lovegrove Review’s findings and their direct application to ALTO’s current trajectory
    Download PDF
    A Published Reference Class

    The cost trajectory the UK Cabinet Office published this month

    The single most useful artefact in the Lovegrove Review is its published trajectory of HS2 Phase 1 cost estimates over time, all expressed in a 2019 price base for comparability. Phase 1 is the London to West Midlands section of approximately 225 km — the only section now being constructed, after the cancellation of Phase 2 north of Birmingham.

    YearPhase 1 cost estimate (£bn, 2019 prices)
    201220.5
    201326.8
    202044.6
    202354
    202466
    202682.2

    In 2019 prices, the 2026 estimate is more than four times the 2012 estimate for the same 225 km of railway. The increase from 2024 to 2026 alone — two years — is larger than the entire original 2012 budget. This is not a critic’s estimate. It is not an academic reconstruction. It is the British government, today, publishing the official trajectory of its own project’s cost.

    For ALTO, the importance of this trajectory is twofold. The comparator is not ancient: HS2 Phase 1 was at roughly the same stage of pre-construction maturity in 2012–2015 that ALTO is at now. And the trajectory is now an official UK government data point — not contested or speculative — which removes one of the standard rhetorical defences used in ALTO’s framing.

    The Canadian Parallel

    The same trajectory has already occurred on the Toronto–Quebec City corridor

    In 2016 the federal government funded a serious study of High Frequency Rail (HFR) for the Toronto–Quebec City corridor: 170–177 km/h conventional rail on largely dedicated tracks, costed at under C$5 billion in 2016 dollars, or under C$10 billion adjusted for construction inflation to 2024. A December 2021 Joint Project Office Business Case prepared by VIA Rail Canada and the Canada Infrastructure Bank confirmed the preferred option. tc.canada.ca

    In March 2022 the federal government issued a Request for Expressions of Interest that pivoted the procurement to a Design-Build-Finance-Operate-Maintain (DBFOM) structure and explicitly invited proposals for speeds above 200 km/h. In February 2025, without publishing a side-by-side comparison of the HFR and high-speed options, the government confirmed the project would become ALTO at 300 km/h+, costed at C$80–120 billion. Passengers will not board until the 2040s.

    ~5×
    HS2 Phase 1 real-terms increase, 2012–2026 (UK)
    Lovegrove Review, May 2026
    16–24×
    HFR to ALTO escalation, 2016–2025 (Canada)
    CRI From HFR to ALTO, March 2026
    $0
    published side-by-side comparison of HFR vs ALTO
    As of May 2026

    The escalation from HFR’s published baseline to ALTO’s announced range is of the same order of magnitude as, and on a comparable timescale to, the four-fold real-terms increase Lovegrove documents for HS2 Phase 1. The HS2 cost-trajectory table above is not a foreign curiosity. It is the comparator for a transformation that has already occurred on the project Canada is now committing to deliver.

    The “Original Sins”

    Lovegrove’s consensus diagnosis — and its ALTO analogues

    Lovegrove summarises the consensus diagnosis of why HS2 cost forecasts proved so wrong. The list is short and direct: original gold-plating of the high-speed concept; a decision to begin construction at the hardest points of the route; changing objectives and political priorities; award of the Main Works Civils Contracts at insufficient design maturity and on terms which did not manage risk; and costs and risks badly underestimated.

    The pursuit of 300 km/h electrified high-speed running across a route with the geological and ecological profile of the proposed southern corridor is itself a gold-plating decision. Reference-class analysis shows that the marginal capital cost of moving from a conventional or near-conventional dedicated passenger railway to a fully grade-separated electrified high-speed alignment is the dominant driver of total programme cost — and is the primary mechanical reason the HFR-to-ALTO transformation generated the cost escalation set out above. An alternative configuration — a lower design speed in the order of 200 km/h, on a route making use of the 401 corridor rather than a new southern alignment across Eastern Ontario — would shift the project into a different cost class and a different environmental and community-impact profile. Whether such a configuration is preferable, on a full set of criteria, is precisely the comparative question the Lovegrove framework says government should answer before a Final Investment Decision.

    The HS2 phasing parallel is not exact: ALTO plans to begin with the Ottawa-to-Montréal segment, which involves real engineering complexity including Leda clay deposits and the Ottawa River crossing, but is not the hardest section of the proposed corridor. The more challenging geological and ecological terrain remains to be worked through downstream of any Notice-to-Proceed-equivalent decision. The category of risk Lovegrove identifies nonetheless applies: committing to a DBFOM contractual architecture spanning the full corridor before the hardest sections have been designed in detail locks in contractual obligations under the same design-immaturity conditions HS2 entered when it awarded its Main Works Civils Contracts. The HS2 mistake was not solely the geographical choice to start in the Chilterns; it was the contractual choice to commit before maturity, and that part of the parallel remains direct.

    Sir Jon Thompson, the Executive Chair of HS2 Ltd, set out the resulting contractual problem directly in evidence to the House of Commons Transport Committee on 10 January 2024. parliament.uk He told the Committee that the Government and the company had decided to let cost-plus contracts under which 99% of the financial risk sat with the Government and only 1% with the contractor, describing the arrangement as extraordinary. Under a fixed-percentage fee, he noted, a contractor who runs over budget receives the same percentage of a much larger number, which effectively incentivises overspending rather than restraining it.

    The risk allocation under the ALTO co-development contract with the Cadence consortium has not been publicly disclosed. Whether it replicates, mitigates, or improves on the HS2 risk allocation cannot be assessed from public information. Under Lovegrove’s framework, that absence of disclosure is itself the relevant problem: the contractual terms that drive cost outcomes over the lifetime of a project are exactly the terms that the sponsor department, Parliament, and the Auditor General require visibility into before, not after, commitment.

    The Crown Corporation Problem

    Lovegrove’s structural critique of the delivery vehicle

    Lovegrove’s most pointed structural critique is of HS2 Ltd’s status as a Company Limited by Guarantee with government as sole guarantor. The Review concludes that this construct was institutionally incoherent. The arguments traditionally offered for it — independence from government, ability to hire at market rates, commercial discipline, decision-making at commercial speed — are real benefits, but they only work when the entity has genuine third-party shareholders with capital at risk.

    “Company structures are arguably fundamentally ill-suited to this type of arrangement.”

    — Lovegrove Review, May 2026

    HS2 Ltd received 100% of its funding from government grant-in-aid. There were no third-party shareholders, no commercial counterparties with capital at risk, no governance mechanisms forcing cost-benefit discipline from below. The advantages of the company form were thus retained only in name. What HS2 Ltd actually got was the freedom to hire at private-sector rates and to operate at arm’s length from ministers, without the corresponding discipline of having investors who would have insisted on cost control.

    ALTO HSR Inc. is in a structurally comparable position to HS2 Ltd at the corporate level. It is a federal Crown corporation, 100% publicly funded, with no third-party shareholders in the corporation itself. The contractual relationship with the Cadence consortium under the DBFOM arrangement is not publicly disclosed in sufficient detail to assess how risk, financing, and return are allocated between the parties or over what time horizon. What can be observed from the public record is the corporate-form question: a Crown corporation receiving 100% of its funding from the federal purse, used to obtain independence from political cycles and freedom to hire specialist talent, is in the same structural category as HS2 Ltd — the category Lovegrove diagnoses as institutionally incoherent because the disciplines that normally accompany the corporate form do not flow from grant-in-aid funding alone.

    The “Fortress Mentality”

    A cultural pathology, and a downstream information failure

    Beyond structure, Lovegrove identifies a cultural pathology that should be familiar to anyone tracking ALTO’s public communications. The Review records that HS2 Ltd’s board, and particularly its executive management and chair, developed what interviewees described as a fortress mentality — becoming cheerleaders not only for HS2 but for the cause of high-speed rail in the UK more generally, framing the project as ushering in a new era. The Review is unambiguous that this conception of the company’s role was misguided. Transport policy is for ministers; the company’s job is delivery within scope and budget.

    “The Board, and especially the executive management and Chair, had adopted a ‘fortress mentality’ and had become ‘cheerleaders’, not merely for HS2 but for the cause of high-speed rail in the UK more generally.”

    — Lovegrove Review, May 2026

    This cultural finding matters because it generated a downstream information failure. Lovegrove quotes board members and reviewers describing the management information packs given to the HS2 Ltd board as forming a veil behind which less good news became difficult to assess or even identify, with the same problem persisting unaddressed years later — packs remaining unwieldy, format-inconsistent, and lacking prioritisation. Because the same data flowed through to government, the sponsor department was working from the same compromised information.

    The CRI’s post-consultation work has documented precisely this pattern in ALTO’s public outputs. The disclosures in Q-923 on cost, ridership, and the self-sustaining claim use confidence framings that do not survive parametric stress-testing against McGill TRAM and Munk School sources. The marketing pivot identified through the Cossette ATI disclosures, and the unanswered status of TRAN Report 18 — published by the House of Commons Standing Committee on Transport, Infrastructure and Communities and left without a government response when Parliament was prorogued — are the documentary symptoms of an executive culture that has begun to treat advocacy as primary and delivery information as secondary. Lovegrove’s framework gives that observation a name and an authoritative diagnostic basis.

    The candour of Sir Jon Thompson’s evidence to the Transport Committee on 10 January 2024 is worth pausing on, because it confirms the Lovegrove diagnosis from inside the institution. Thompson — himself a former Permanent Secretary at HM Revenue and Customs and at the Ministry of Defence, and a double-qualified accountant — told the Committee that when he joined the HS2 board in 2021 he was struck by the lack of data and scrutiny of programme finances; that the management information presented to the board was not robust enough to assess whether main civils contractors were meeting productivity targets; and that significant improvement only arrived in October 2023, two and a half years later. He described it as a shocking thing to say, but acknowledged that the quality of board-level management information had not been good enough. That is the senior executive of a major UK arm’s-length delivery body, on the parliamentary record, confirming the exact information failure the Lovegrove Review now documents externally.

    The Notice-to-Proceed Moment

    When external reviews substitute for official advice

    The Lovegrove Review devotes substantial attention to the Notice to Proceed decision in early 2020, when government formally committed to construction of HS2 Phase 1. The sequence is instructive. The Oakervee Review, an independent panel chaired by a former HS2 Ltd chair, recommended proceeding with the full route. Its report was published shortly after a Prime Minister–Chancellor–Secretary of State trilateral meeting had already reached the same conclusion. The formal Notice to Proceed was confirmed in March 2020.

    Lovegrove’s criticism is not that the Oakervee Review was conducted in bad faith. It is that the official advice provided to ministers alongside the Oakervee report did not address alternative ways of delivering the project — as distinct from alternative projects — including options which would have led to a delay in construction while alternative designs, options, or contractual arrangements were sought. The external review effectively substituted for official advice on strategic choice.

    “Reviews by external actors (including this one) have their place in informing policy formulation, but they should not substitute for official advice.”

    — Lovegrove Review, Recommendation 14

    This is the recommendation with the most direct bearing on where ALTO now sits. The work being produced by Cadence under its co-development contract, the public outputs of ALTO HSR Inc., and the materials prepared for the parliamentary process are all in danger of functioning as external review substituting for official advice on alternatives. The category of alternative Lovegrove insists should not be foreclosed before a Final Investment Decision — different speed classes, different route alignments, different contractual structures, different phasing — is exactly the category that has not been comparatively analysed for ALTO. A lower design speed in the order of 200 km/h, and a route making use of the 401 corridor rather than a new southern alignment, are concrete examples of the alternatives that would normally be costed and compared at this stage. They have not been.

    The CRI’s March 2026 brief From HFR to ALTO already constitutes the kind of structured comparison Lovegrove says government itself should produce. It identifies eight pivotal changes that occurred between the December 2021 HFR Business Case and the February 2025 confirmation of ALTO as a high-speed system, and documents the absence of a published side-by-side cost-benefit comparison between the two options. The point under Lovegrove’s framework is not that citizen research is a substitute for official advice. It is that when an arm’s-length delivery body and the sponsor department do not produce that comparison themselves, and the government nonetheless proceeds, the conditions Lovegrove identifies as the proximate cause of the HS2 failure are present.

    Vindication of the Dissenting Voice

    The lone dissenter the Cabinet Office now says was right

    One paragraph of the Lovegrove Review deserves to be read by every parliamentarian considering ALTO. When the British government was deciding whether to proceed with HS2 in 2020, it commissioned an independent panel chaired by a former HS2 chair, Douglas Oakervee. The panel recommended proceeding with the full project. One member dissented — Lord Berkeley, a peer and former rail executive. His dissenting report cast doubt on the costings, the schedule, and the capability of HS2 Ltd to manage the project. He was dismissed at the time as methodologically unsound. His report was excluded from the panel’s formal conclusions.

    “There is no escaping the fact that the thrust of his judgements, in particular about the capability of the Company to manage the project, have proved to be correct, and his estimates much closer to today’s outturn than those upon which ministers ultimately gave the go-ahead.”

    — Lovegrove Review, May 2026

    That is the UK Cabinet Office, six years later, on the public record, telling Parliament that the man it ignored was right. His estimates were closer to reality than the ones ministers used to make the final decision. The institutional process designed to test his concerns failed.

    This matters for Canada because it is the most authoritative statement any G7 government has ever made about the value of structured outside-the-tent analysis on a major infrastructure project. It does not validate every dissenting analysis automatically — Lovegrove notes that some of Berkeley’s specific methodological steps were questionable and that some of the cost increases arose from factors Berkeley did not identify — but it establishes that the dismissal of dissenting reference-class work as inherently less credible than insider forecasts has now been formally repudiated by one G7 government.

    Corporate Overlap

    Two Cadence members were inside HS2

    Two of the six members of the Cadence consortium selected by Canada to design, build, finance, operate and maintain ALTO were directly embedded in HS2 work during the period that the Lovegrove Review now criticises.

    AtkinsRéalis

    The Canadian engineering firm that rebranded from SNC-Lavalin in 2023, and the lead Canadian engineering member of Cadence, was part of the CH2M / Atkins / SENER Engineering Delivery Partner joint venture for HS2 Phase One. That ten-year contract was awarded in 2016 and was valued between £250 million and £350 million. The Engineering Delivery Partner role placed Atkins inside HS2 Ltd, fully integrated, with explicit responsibility for supporting the preparation and procurement of the Main Works Civils Contracts — the contracts that the Lovegrove Review identifies as awarded at insufficient design maturity and on terms which did not manage risk. Atkins’s UK arm was acquired by SNC-Lavalin in 2017, mid-way through the contract, and is now part of AtkinsRéalis.

    SYSTRA

    The French rail engineering firm and a Cadence member was part of the Mott MacDonald / SYSTRA design joint venture working alongside the Balfour Beatty VINCI construction joint venture on HS2 Lots N1 and N2 of the Main Works Civils Contracts — the 90 km West Midlands stretch including the Long Itchington Wood Green tunnel and the Birmingham approaches. SYSTRA was also a partner in the BBV-SYSTRA (BBVS) joint venture for the Old Oak Common station in London. SYSTRA’s role on HS2 was thus across both design and construction-management functions on the very contracts whose financial architecture HS2’s own chair has publicly criticised before the UK Public Accounts Committee.

    These observations are factual, not attributive. The Lovegrove Review is explicit that the institutional failure on HS2 lay primarily with HS2 Ltd’s governance and culture and secondarily with the Civil Service, not with the contractor firms per se. Many of the firms involved are world-leading rail engineers, and their inclusion in Cadence reflects that. The point is that two firms whose immediately prior major HSR engagement is now the subject of a Cabinet Office post-mortem on cost control are now central to ALTO’s design, build, and ongoing operation under a DBFOM structure. For parliamentarians and analysts considering whether the lessons of HS2 are being absorbed into ALTO’s procurement and oversight, this is a fact that warrants disclosure in any briefing material on the project.

    Implications for ALTO

    What this changes

    Canada has the same parliamentary system as the United Kingdom. The same Treasury Board controls. The same Crown corporation tools. The same Public Accounts Committee. The same Auditor General. The institutional architecture that failed at HS2 — and that Lovegrove has now diagnosed in unusual detail — is the architecture being used to deliver ALTO.

    The HS2 cost trajectory is now an official G7 reference class

    The Cabinet Office published trajectory — £20.5bn (2012) to £82.2bn (2026) in constant 2019 prices — is now an official G7 data point. It belongs in every cost-related submission, briefing letter, and parliamentary communication on ALTO between now and a Final Investment Decision.

    The Crown corporation critique applies directly

    The structural critique of the Company Limited by Guarantee model translates directly to ALTO HSR Inc. The case for Crown-corporation delivery has been overstated; the commercial discipline its proponents claim does not flow from the structure adopted when 100% of funding comes from the public purse.

    Recommendation 14 creates a concrete obligation

    Government, not contractors, must produce the comparative analysis of alternative ways of delivering the project — including alternative speed classes and route corridors — before any Notice-to-Proceed-equivalent decision. Doing it after commitment is, in Lovegrove’s framework, too late.

    Berkeley’s vindication establishes a precedent

    The Cabinet Office’s 2026 vindication of Lord Berkeley’s 2020 dissenting report establishes a public-record precedent for the credibility of structured citizen reference-class analysis in HSR governance. That precedent is now available to be cited.

    The AtkinsRéalis / SYSTRA overlap warrants disclosure

    The involvement of two Cadence members in the HS2 work the Lovegrove Review now criticises is a material fact for parliamentarians considering whether ALTO’s procurement reflects institutional learning from HS2, or the application of the same contractual architecture in a different jurisdiction.

    The Lovegrove and Stewart Reviews together represent the most current, most senior statement by a G7 government on what arm’s-length high-speed rail delivery requires of a Westminster-system sponsor department. The lessons set out in the Lovegrove Review are not lessons Canada needs to learn the hard way. They are available now.

    Download Full Brief
    Reading Lovegrove (PDF)
    Complete analysis for parliamentarians, the Parliamentary Budget Officer, the Auditor General, and constituents tracking ALTO’s governance and procurement
    Download PDF
    Sources

    Primary documents and statements

    1.
    Lovegrove, Sir Stephen. Review of implications for the Civil Service and wider public sector of findings of the James Stewart Review. Cabinet Office, May 2026. Published under Open Government Licence v3.0. gov.uk
    2.
    Stewart, James. The HS2 Experience: Major Transport Projects Governance and Assurance Review. 2025.
    3.
    Thompson, Sir Jon, Executive Chair, HS2 Ltd. Oral evidence to the House of Commons Transport Committee, HS2: progress update, HC 85, 10 January 2024, Questions 393–471 (in particular Qq. 410–412 on cost-estimation methodology, Q417 on the 99/1 risk allocation under cost-plus contracts, Q428 on inadequacy of board-level management information, and Q435 on the limits of corrective action under existing contractual fundamentals). parliament.uk
    4.
    Lord Berkeley. HS2 Review Dissenting Report, January 2020.
    5.
    Government of Canada / Cadence Consortium. Announcement of selection of Cadence as preferred private developer partner for the ALTO HSR project, February 2025.
    6.
    Joint Project Office (VIA Rail Canada / Canada Infrastructure Bank). High Frequency Rail Project Business Case Update. December 2021.
    7.
    Transport Action Canada. Statement on the selection of the Cadence consortium for ALTO HSR co-development. February 2025. transportaction.ca
    8.
    ALTO HSR Citizen Research Initiative. From HFR to ALTO: How a $5 Billion Plan Became an $80–120 Billion One. March 2026.