Tag: farm severance

  • Counting the crossings

    Counting the Crossings

    ALTO says it will not wall off communities, and points to France and Spain. Those countries did something else as well, and the letter leaves it out.

    ⚠ What ALTO Told Kingston Readers

    On 14 August 2026, a letter in the Kingston Whig-Standard from ALTO’s Chief Project Management Officer and Cadence’s Project Director told corridor residents the railway “will not create a wall between communities”, nor a barrier to wildlife or water. As proof it can be done, the letter offered two numbers: France has built more than 4,000 structures across roughly 2,700 km of high-speed line, and Spain more than 900 across roughly 750 km.

    The letter does not mention Kingston, the route, where stations would go, what any of it costs, or expropriation. It does say preserving access has been a key principle from the beginning. ALTO’s own Preserving Access and Movement page carries a last-modified date of 7 May 2026 — after the consultation closed on 24 April.

    The Short Version

    Take ALTO’s own figures and divide them through. France works out to about one structure every 675 metres. Spain, about one every 833 metres. Those are the rates being offered as reassurance.

    The trouble is that a count of structures built tells you nothing about how many crossings were closed. A railway can put in 900 bridges and still cut off 3,000 field entrances, farm lanes and township roads. The letter gives the top half of the fraction and leaves out the bottom.

    Kingstonians already have ALTO’s own answer to this. In February 2026, ALTO’s Vice-President of Systems Engineering told Kingston City Council that crossings would be consolidated to bring costs down, and that the company would try to limit how many overpasses get built. That was six months before the letter, to the same city, on the same subject.

    There is a larger omission. France did not solve farm severance with bridges. It has a legal procedure that lets the state reorganise the surrounding farmland so that a farm cut in two can be put back into a workable shape, paid for by the project. On one French high-speed line, 3,700 hectares of land were bought up in advance so that farmers could be compensated in land rather than only in cash. Ontario has nothing of the kind.

    Download
    Counting the Crossings — Full Brief (PDF)
    The arithmetic behind ALTO’s France and Spain comparison, and the land instrument the letter leaves out

    Download PDF

    The Arithmetic

    What ALTO’s own numbers work out to

    Neither figure in the letter is disputed here. They are simply divided through. A structure count only becomes meaningful once you know how far apart the structures are, and how far apart the things they are meant to replace used to be.

    ~675 m
    average gap between structures on the French network, using ALTO’s figures
    4,000 structures over 2,700 km
    ~833 m
    average gap on the Spanish line ALTO cites
    900 structures over 750 km
    1.25–2 km
    typical spacing of public roads across eastern Ontario’s concession grid
    before counting farm lanes and driveways

    There is a third number the letter does not offer, and it cuts the other way. HS2 in Britain is the most recent comparable project of this kind: a brand-new high-speed line built through peri-urban and rural England. Its first phase runs about 225 km and will carry more than 500 bridging structures, including over 50 major viaducts — roughly one structure every 450 m. That is about half again the French rate, through country a good deal more built up than eastern Ontario. The most recent comparable project provided more, not fewer, than the average ALTO offers as reassurance.

    The spread between the three is itself worth noticing. A fifty per cent difference between two European networks tells you that these totals are governed by terrain, by how much of a route sits in tunnel or on viaduct, and by what each project counts as a structure. About nine tenths of HS2’s first phase runs in tunnel, in cutting or on structures, so a large share of those 500 exist to carry the railway over the landscape rather than to carry a community across the railway. A structure count is a construction statistic, not a standard of community access.

    Eastern Ontario was surveyed on a grid. Roads run at regular intervals, and between them sit farm lanes, private driveways and municipal drains. Whether a European average is enough for that grid is exactly the question people along the corridor are asking. Quoting the French figure does not answer it. It assumes the answer.

    There is a comparison closer to home that nobody has yet made. Highway 416 is a modern, fully grade-separated corridor built through the same survey grid, the same farmland and several of the same municipalities. How many crossings Ontario provided on that road is not something this brief has established, but it is the obvious yardstick, and it ought to be established before a French average is relied on.

    The Missing Number

    How many roads are we talking about?

    The denominator is not actually a mystery. Canada’s own transport department has published it.

    In a briefing note prepared for a Parliamentary committee in March 2023, Transport Canada set out what a full high-speed line between Québec City and Toronto would require: a fully enclosed and fenced corridor, a straighter alignment, double tracking throughout, and complete grade separation on a route that currently carries more than 1,000 public and private crossings.

    That figure described the northern route, through comparatively empty country — Canadian Shield, wetlands, big rural lots. The southern corridor now being prioritised runs through some of the most intensively farmed land in eastern Ontario, where the concession grid is tightest. On the southern option, 1,000 is more likely a floor than a ceiling.

    The Initiative’s own road severance analysis puts the proportion of crossings permanently closed rather than bridged on rural high-speed corridors at somewhere between 30 and 60 per cent. Applied to a floor of 1,000, that is 300 to 600 roads dead-ended — our estimate, not a figure ALTO or Transport Canada has published.

    1,000+
    public and private crossings on the alignment
    Transport Canada, March 2023
    300–600
    roads likely closed, on the Initiative’s estimate
    30 to 60 per cent of crossings
    $3.2–8.4B
    Initiative’s estimated cost of the crossings that would be built
    never shown as a separate line

    That last figure matters for a different reason. Grade separation is one of the most expensive parts of any high-speed corridor, and a sum of that size has never appeared as its own line in ALTO’s published capital estimate. Neither has any methodology explaining how many crossings will be built, or to what standard, or how it will be decided which roads are simply stopped up.

    The reassurance in the August letter is offered in the absence of the one document that could support it. Further detail is set out in the Initiative’s technical analysis of road severances.

    On the Record

    What ALTO told Kingston in February

    Six months before this letter appeared in Kingston’s paper, ALTO’s Vice-President of Systems Engineering and Interface sat before Kingston City Council and was asked about exactly this. The transcript is the fullest account ALTO has given in public of how it approaches road crossings, and it does not read the way the letter does.

    The reassurance

    Asked by a councillor whether there would be a standard distance between crossings, he described a working assumption that every road would get some form of duct or overpass, since the roads belong to municipalities or road authorities and cannot be cut unilaterally.

    The qualification, in the same answer

    He went on to say that in reality some crossings would be looked at for consolidation, to lower costs and improve construction, subject to discussion with the road authority.

    The objective

    Pressed by the Deputy Mayor, he set it out plainly: grade separations would vary by area, would be settled during route selection, and ALTO would “try and limit the number of overpasses that we’ll need to get created”.

    And the fencing

    He confirmed that modern high-speed rail must be completely segregated and fully fenced anywhere level access is possible, whether the line runs at 200 or 300 km/h.

    Read together: a starting assumption that is subject to cost-driven consolidation, an explicit goal of building as few overpasses as possible, and continuous fencing between whatever crossings survive.

    The councillor’s actual question — is there a standard distance between crossings — was not answered, and no standard has been published since. February’s statements and August’s letter were addressed to the same city.

    Three Problems

    Why the structure count does not settle it

    You are being shown half a fraction

    The number that answers the severance question is a ratio: structures built, divided by accesses cut off. The letter supplies only the first. Every complaint recorded by French and Spanish farmers over the last forty years is perfectly compatible with the figures quoted.

    Not every structure reconnects anything

    “Engineering structures” and “viaducts” include everything the railway needs to build itself: bridges over rivers, crossings of existing motorways and railways, tunnels through hills. A viaduct over a river gorge restores nobody’s access to their back field. How many of the 4,000 exist to reconnect a severed local road or laneway is not stated, and is certainly a much smaller number.

    A different landscape

    The French network largely runs through consolidated farming country. Eastern Ontario is a survey grid of concession roads, side roads, long farm lots and dead ends. The same rate of crossings produces a very different result depending on how much there was to cross in the first place.

    The Missing Piece

    What France also built

    The most important thing missing from the letter is not a number. It is a law.

    Two of the countries with the longest high-speed rail experience did not leave farm access to be worked out project by project. They legislated it. France did so through its rural code; Germany passed a federal land consolidation statute in 1953 that covers exactly this situation. In both, farmers sit on the body that decides, that body can compulsorily redraw the farms and the farm tracks together, the proponent pays, and there is a right of appeal to the courts.

    France has a statutory procedure called aménagement foncier agricole et forestier — land reorganisation, formerly known as remembrement. Its stated purpose includes repairing the damage that major linear projects, high-speed railways among them, do to rural land. Where a line slices a farm in half, the surrounding parcels can be legally reorganised so that holdings are handed back in a shape a farmer can actually work. Local commissions run it under departmental authority, and the project pays for it.

    Land is also bought up ahead of time. A national rural land agency, SAFER, holds first refusal on farmland coming up for sale, so that displaced farmers can be given land instead of only a cheque. Spain has its own version of the same idea.

    This matters for who gets a say. In Canada there is no seat and no statutory role. On 4 June 2026 the five organisations representing effectively the whole farm sector in Ontario and Quebec concluded that ALTO’s proposed collaboration agreement was not in their members’ interests to sign. In France they would not have had to negotiate for a place at the table. They would already have had one, in law.

    This is not a minor administrative detail. On the Le Mans to Rennes high-speed line, roughly 3,700 hectares were placed in reserve, with agricultural land bought up as it came to market within three kilometres of the future route. In Ille-et-Vilaine alone, 48.5 km of new railway took about 480 hectares of crops and pasture — and against that, 720 hectares of land reserve were assembled and parcels across some 1,200 hectares either side of the track were reorganised, affecting more than 4,400 landowners, financed by the project and delivered through intercommunal commissions.

    In France and Germany In Ontario
    A legal procedure to reorganise farmland around a new line, whose express purpose includes repairing damage done by major linear infrastructure. No equivalent. There is no statutory land reorganisation for farms severed by infrastructure.
    Farmers hold seats on the deciding body, and decisions can be appealed to the courts. No seat and no statutory role. Five farm organisations declined ALTO’s collaboration agreement in June 2026 rather than accept its terms.
    A rural land agency with first refusal on farmland coming to market, used to assemble land reserves years ahead of construction. No equivalent agency and no statutory land reserve mechanism.
    Local commissions empowered to redraw parcel boundaries, operating under departmental authority. No equivalent body. No one can redraw the neighbours’ boundaries to make a severed farm whole again.
    Compensation in land is possible: a farmer who loses acreage can be given workable acreage back. Compensation in money only, for what is physically taken. Expropriation and negotiated purchase are the available tools.

    So the comparison in the letter is accurate and, at the same time, does not carry over. The French result rests partly on a legal instrument Canada does not have. A letter that cites France’s bridge count while saying nothing about France’s land reorganisation is describing half of how the problem was solved.

    Cadence’s Project Director is quoted in French farming trade coverage of that same Le Mans to Rennes project, explaining that the land reserve had to account for the right-of-way, the land reorganisation and the environmental compensation together.

    That gap is a problem in Canadian law rather than a failing of the project sponsor. It is still a gap, and it has to be closed before European results can reasonably be promised here. Closing it is not something ALTO can do on its own.

    Not Just How Many

    A structure is not automatically an answer

    Even where a crossing is built, two questions decide whether it is any use, and ALTO has published nothing on either.

    Size

    A livestock crossing and a machinery crossing are not the same structure. A standard cattle underpass runs about 2.1 metres high. A modern combine or grain cart needs 4 metres or more. A structure built to the wrong dimension is a closure as far as the equipment is concerned. No minimum dimensions have been published, and no spacing standard.

    Upkeep

    Nobody has decided who maintains these crossings over the decades that follow. ALTO describes its approach as still being developed. France took roughly a decade of litigation and legislation to settle the same question. Municipalities along the corridor have a direct interest in the answer.

    What closure pushes onto the road

    When a farm crossing is extinguished, the equipment does not disappear. It goes onto the public road. By the Ontario Federation of Agriculture’s own figure, slow-moving farm vehicles are 3.8 to 4.8 times more likely to be involved in a fatal collision per kilometre travelled. Severance is therefore also a road-safety question, and one that has not been assessed.

    The Initiative has examined the two halves of this problem separately: road severances and wildlife crossings.

    The Wall

    One claim that cannot be tested as written

    A railway running at over 300 km/h is fully grade-separated and fenced along its entire length. That is what grade separation means. The structure is a continuous barrier by engineering necessity. The real question is where the openings are and how many there are, not whether the barrier exists.

    What ALTO could reasonably promise is that severance will be mitigated at designed crossings, to a stated standard, at a stated spacing. A flat undertaking that no wall will be created is not something anyone can test — and it is a sentence that will be read back to ALTO by every landowner and every township that later finds an access closed.

    The same applies to wildlife. Continuous fencing is a barrier to animals except where crossings are designed in, and how well those crossings get used varies a great deal by species — a question examined at length in the Initiative’s work on wildlife crossings.

    An early study along a Spanish high-speed line, monitoring fifteen underpasses and two overpasses over two years, recorded no deer or wild boar crossings at all. That was 1996, and crossing design has moved on a great deal since; it should not be read as the last word. But the more recent evidence does not settle the question the other way either. A systematic review of crossing structures across roads and railways found that animals did cross them in almost every study examined — and yet a decline in wildlife movement after construction was prevented in fewer than 40 per cent of cases, with many structures poorly built or poorly monitored.

    On Spain’s network the best-documented harm is to birds. Camera monitoring from on board trains estimated 60.5 bird collisions per kilometre per year on a stretch carrying 53 trains a day, and 26.1 on a stretch carrying 25. Later work found the surrounding bird community changing species by species, and uncapped catenary poles acting as pitfall traps for birds that nest in cavities. Anti-birdstrike screens are routinely fitted to viaducts, and how well they work is still being studied.

    None of this says the corridor cannot be crossed by wildlife. It says that whether it can depends on design decisions and monitoring commitments not yet made, and that a flat undertaking given before them is not one a reader can test. Of the three promises, the one about natural water flows is the most straightforward to deliver.

    What Can Be Asked Now

    Six questions ALTO can answer today

    The letter makes commitments specific enough to be checked. None of the following requires a finalised route.

    The ratio
    Against Transport Canada’s figure of more than 1,000 crossings, how many are assumed to get a structure, and how many will be closed?
    Composition
    Of the French and Spanish structures cited, how many exist to reconnect a severed local access, as opposed to carrying the line over a river, motorway or railway?
    Ontario benchmark
    What crossing rate is assumed for the Ontario segments, and how was it arrived at? A comparison with Highway 416 through similar country would be useful to communities along the route.
    Criteria
    What method decides whether a road is bridged or dead-ended, and what detour distance is treated as acceptable in the countryside?
    Cost
    What provision for grade separation sits inside the capital estimate, and why has it never been shown as a separate line?
    Dimensions
    What minimum height and width will agricultural crossings meet, and what spacing standard applies? Will structures be sized for machinery or only for livestock?
    Maintenance
    Who owns and maintains each crossing structure over its life, and who carries that cost — ALTO, Cadence, or the municipality?
    Detours
    Where an access will not be reinstated, how much further will people have to drive to reach the nearest crossing, and what work supports that figure?
    Emergency access
    Which paramedic services and municipal fire departments have been consulted about response routes, on what dates, and what did they find?
    Severed farms
    Is any land reorganisation or land reserve contemplated for farms cut in two, and under what legal authority would it operate?

    The letter is right that decades of international experience exist and should be drawn on. The difficulty is that it draws on one half of that experience and leaves out the other. France built more than four thousand structures. France also rebuilt the farms. The second of those depended on machinery Ontario does not have, and no number of overpasses substitutes for it. Meanwhile the company’s own engineering executive has told this city’s council that the aim is to build as few overpasses as it can.

    Download Full Brief
    Counting the Crossings (PDF)
    Full analysis for municipal councils, farm organisations, MPs and residents along the corridor — with the per-kilometre working, the French statutory provisions and the complete source list

    Download PDF

    How to read the numbers on this page

    The French and Spanish structure counts are as given in the 14 August letter and used here as stated. The Transport Canada crossing count, the HS2 figures, the Kingston council statements, the French statutory provisions, the HS2 petition figures, the emergency-response research and the wildlife findings are all quoted from the sources listed below and can be checked there.

    Everything else is our own calculation or estimate, and is marked as such where it appears: the per-kilometre and spacing rates, the 30 to 60 per cent closure proportion and the 300 to 600 closures that follow from it, the $3.2 to $8.4 billion grade-separation range, and the detour arithmetic. Where ALTO or Transport Canada has not published a figure, we say so rather than inferring one, and we make no claim about what anyone knew or intended.

    Sources

    Primary documents and statements

    1.

    Maria Luisa Dominguez and Loïc Dorbec, “Building on decades of high-speed rail experience,” letter to the editor, Kingston Whig-Standard, 14 August 2026. Structure and length figures for France and Spain are as stated in that letter and are used here as given; the per-kilometre rates are the Initiative’s arithmetic.
    2.

    Chambres d’agriculture France, on aménagement foncier agricole et forestier and its role in repairing disruption caused to rural land by the route of major linear works, high-speed railways included. chambres-agriculture.fr
    3.

    Département d’Ille-et-Vilaine, on the LGV Bretagne–Pays de la Loire land reorganisation and land reserve programme: 48.5 km of new line, 480 ha absorbed, 720 ha of reserve constituted, 1,200 ha of parcels reorganised, more than 4,400 landowners affected, financed by the project owner. cg35.fr
    4.

    WikiAgri, on the land reserves assembled through SAFER for the Le Mans–Rennes high-speed line: approximately 3,700 ha placed in reserve, with agricultural land pre-empted within three kilometres of the future alignment. Contains the quoted remarks of Cadence’s Project Director on the composition of that reserve. wikiagri.fr
    5.

    Transport Canada, TRAN Committee Appearance Binder, Item 15: High Frequency Rail, 7 March 2023 — source of the figure of more than 1,000 public and private crossings on the alignment.
    6.

    City of Kingston, Council meeting of 17 February 2026, closed-captioning transcript — remarks of ALTO’s Vice-President of Systems Engineering and Interface on crossing consolidation, overpass numbers and corridor fencing.
    7.

    HS2 Phase 1 structure count: more than 500 bridging structures including over 50 major viaducts, per HS2 Ltd’s head of civils structures, reported in New Civil Engineer, 15 June 2022, and repeated on the Institution of Civil Engineers project page. Route length taken as approximately 225 km; some sources give 208 route km, which would raise the per-kilometre rate rather than lower it.
    8.

    Wildlife. Rodríguez, Crema and Delibes (1996), on underpass and overpass use along Spanish high-speed line. Rytwinski and others, systematic review and meta-analysis of crossing-structure effectiveness, for the finding on movement decline. Barrientos and Borda-de-Água, “Railways as Barriers for Wildlife: Current Knowledge,” in Railway Ecology (Springer, 2017). García de la Morena and others (2017) for the on-board camera collision estimates; Malo and others (2017) on bird response and catenary-pole mortality; and work on high-speed rail and bird-community change published in PLOS One (2024).
    9.

    Erin Durant, “Alto: Which farm roads stay open and who pays?” 16 August 2026 — source for the German Flurbereinigungsgesetz parallel, the seats-and-appeal structure of the French and German commissions, crossing dimensions for livestock versus machinery, the unresolved maintenance question, the OFA slow-moving-vehicle collision figure, and the last-modified metadata on ALTO’s agricultural pages.
    10.

    Joint statement of the Ontario Federation of Agriculture, l’Union des producteurs agricoles, National Farmers Union (Ontario), Christian Farmers Federation of Ontario and Union des cultivateurs franco-ontariens, 16 June 2026, following their 4 June meeting on ALTO’s proposed collaboration agreement.
    11.

    ALTO HSR Citizen Research Initiative, Road severances (technical analysis, March 2026 — source of the closure proportions and grade separation cost range) and Wildlife crossings.
    12.

    Ontario road spacing reflects the concession survey pattern across the corridor study area. Highway 416 is proposed here as a benchmark for comparison; no crossing-provision figure for that corridor has been established for this brief.
  • 500 Farms

    Five Hundred Farms

    ALTO’s agricultural commitments measured against the public demands of Canada’s farm associations.

    ⚠ New Disclosure: ALTO CEO Confirms Acquisition Footprint

    ALTO chief executive Martin Imbleau has publicly estimated that approximately 1,700 properties would be acquired on the Ottawa–Montreal first segment alone — the initial phase of construction within the broader 1,000 km Toronto–Quebec City corridor — of which approximately forty per cent, or roughly 500, would be farmland. Land acquisition on this segment is to begin in late 2026 or early 2027, ahead of the 2029 construction start. Imbleau directly confirmed that some expropriation will be required. CFRA / Substack   CBC / Radio-Canada

    ALTO has not yet disclosed a comparable property or farm count for the remainder of the corridor (Ottawa–Peterborough–Toronto, and Montreal–Trois-Rivières–Quebec City). The agricultural footprint of the full network is therefore expected to be substantially larger than the figures above.

    Critical Finding

    Across the four major Canadian farm associations whose demands are operational rather than structural — OFA, UPA, CFA, and BFO — ALTO’s published agricultural framework substantively addresses one demand (tile drainage protection), partially addresses three (independent appraisals, third-party costs, qualitative crossings reference), and does not meet five (independent agricultural impact assessment before route selection; binding farm-access guarantees with minimum dimensions and spacing; protection of all actively farmed lands; recognition that HSR’s permanent impact is more significant than highways or transmission lines; and the four associations’ shared call for a project pause).

    The 500-farm figure is not, in percentage terms, large at the national or provincial scale. It is substantial in the geographic clusters where the alignment runs. ALTO’s chief executive’s disclosure forecloses the response that has been available until now — that agricultural impacts are speculative pending corridor selection. The associations are not asking for revisions to a framework whose existence they accept. They are, with the partial exception of NFU’s structural framing, asking for assessments that have not been done and protections that have not been committed.

    Two contextual findings frame the comparison that follows. The High-Speed Rail Network Act, enacted as Division 1 of Part 5 of Bill C-15 and given royal assent on March 26, 2026, modifies the standard federal expropriation regime for these acquisitions in four specific ways. And the most-cited academic survey of public support for the project — the Transportation Research at McGill corridorwide study (Zhang, Negm, El-Geneidy, 2025) — did not sample the rural communities along the corridor whose land would be acquired.

    Download
    Five Hundred Farms — Full Brief (PDF)
    Comprehensive demand-by-demand comparison of ALTO’s published commitments with the public positions of OFA, UPA, CFA, BFO, and NFU
    Download PDF
    The Footprint

    What 500 farms means in operational terms

    The May 2, 2026 disclosure is the first public quantification of the project’s agricultural footprint by ALTO itself, given in an interview with Andrew Pinsent published on Substack and aired on News Talk 580 CFRA. Three days later, Radio-Canada’s Mathieu Berger reported the same figures with a clarification on geographic scope: the 1,700 properties / 500 farms estimate applies to the Ottawa–Montreal first segment, not to the full 1,000 km Toronto–Quebec City corridor. The Pinsent interview also confirmed the acquisition timeline on this first segment.

    ~1,700
    properties to be acquired on the Ottawa–Montreal first segment
    Imbleau, May 2 interview
    ~500
    farm properties on the Ottawa–Montreal first segment (~40% of acquisitions)
    Imbleau, May 2 interview
    2026/27
    land buying begins on Ottawa–Montreal segment
    ahead of 2029 construction start

    Five hundred farms on the Ottawa–Montreal segment alone is not a small number for the affected agricultural communities. The Ontario Federation of Agriculture represents 38,000 farm families across Ontario; l’Union des producteurs agricoles represents 42,000 producers and 163,000 forest landowners in Quebec. As a percentage of the national or provincial farm population, 500 properties is a small share. As a count of farms in the specific geographic clusters along the proposed first segment, it is substantial — concentrated along the Ottawa–Montreal route through eastern Ontario and the agricultural regions of Quebec immediately east of the Ottawa River. The agricultural footprint of subsequent segments — Ottawa–Peterborough–Toronto, and Montreal–Trois-Rivières–Quebec City — has not been publicly quantified by ALTO; the cumulative total will be substantially larger than five hundred farms once the full network is mapped.

    Five hundred farm properties also represents a structural footprint at the landscape scale. With a 60-metre fenced right-of-way between three-metre security walls, no level crossings, and the engineering requirement that any tens-of-metres alignment adjustment requires approximately seven kilometres of straightening to recover, the corridor’s geometry is highly constrained. Five hundred farms means roughly five hundred site-specific severance, access, and drainage problems to solve, each shaped by local topography, the layout of the existing farm operation, and the position of the rail alignment relative to active fields, laneways, water sources, and farm buildings.

    ALTO’s published timeline now compresses what is operationally possible between corridor narrowing and acquisition. The Ottawa–Montreal corridor is to be narrowed from approximately ten kilometres to approximately sixty metres in autumn 2026. Formal letters to property owners affected by the narrowed corridor will be sent before the narrowed corridor is publicly disclosed. By the time agricultural impact assessment, mitigation framework development, and binding farm-access guarantees would have to be in place to meaningfully precede acquisition, the corridor will already be selected. Substantive change to the alignment will, by ALTO’s own engineering disclosure, no longer be possible at the metre or property scale once that selection is made.

    The Procedural Context

    A different regime applies to these 500 farms

    The 500 farm properties on the Ottawa–Montreal first segment do not sit within the standard federal expropriation regime that applies to other federal land acquisitions. On March 26, 2026 — 29 days before the ALTO consultation deadline of April 24, 2026 — the Budget Implementation Act, 2025, No. 1 (Bill C-15) received royal assent. Division 1 of Part 5 of that Act enacts the High-Speed Rail Network Act (HSRN Act), which establishes a project-specific statutory framework for the Toronto–Quebec City corridor and substantially modifies the procedural rights of affected landowners.

    Four operative provisions of the HSRN Act materially differ from the standard Expropriation Act regime that would otherwise apply:

    Section 17(2) — No required attempt to purchase

    Under section 4.1 of the standard Expropriation Act, the Crown must generally attempt to negotiate a purchase before resorting to expropriation. The HSRN Act removes this precondition for any “interest or right required for the high-speed rail network.” The Crown may proceed directly to expropriation without first attempting to buy the land.

    Section 17(3) — Ministerial discretion foreclosed

    The appropriate Minister “is deemed to be of the opinion” that the land is required for a public work, and “must” expropriate. The standard public-purpose determination is statutorily presumed rather than weighed on the facts.

    Sections 18(1) and 18(2) — Public hearing process removed

    Sections 8, 9, 10 and 11 of the Expropriation Act do not apply. The right to a public hearing before a hearing officer when an objection to expropriation is filed is removed. Affected owners retain a 30-day window to file a written objection under section 21 of the HSRN Act, but no hearing — no oral testimony, no cross-examination of the Crown’s evidence, no public record of the objection process.

    Section 23 — Market value exclusion

    Increases in value resulting from work undertaken after a prohibition-on-work notice has been registered are excluded from compensation. Owners who improve their land between notice and expropriation cannot recover the value of those improvements.

    The Standing Senate Committee on Transport and Communications, in its February 12, 2026 report on the relevant divisions of Bill C-15, recorded that “some witnesses highlighted the significant expropriation powers granted to the federal government as part of the HSR project, in particular emphasizing the removal of the public hearing process set out in the Expropriation Act.”

    The combined effect is that the 500 farms on the Ottawa–Montreal first segment will be expropriated under a more constrained procedural regime than would apply to any other federal land acquisition outside the HSR corridor. The framework ALTO has published — and against which this brief measures the agricultural associations’ demands — operates within this statutory context. The associations’ calls for independent assessment and meaningful consultation are made by communities whose standard procedural rights have already been narrowed by federal statute.

    The empirical gap

    The most-cited academic study of public support for the project — High-Speed Rail in Canada: Insights from a corridorwide survey and a financial analysis, published by Transportation Research at McGill (Zhang, Negm, El-Geneidy, 2025) — provides the headline finding that nearly 90 per cent of respondents perceive substantial benefits for Canada’s economy, international image, tourism, environment, and home regions’ growth. The figure has been cited as evidence of broad public support for the project.

    The McGill survey did not, however, sample the corridor landowners whose property would be acquired. Recruitment was conducted in October 2025 via paid advertisements on Facebook and Instagram targeting users within six Census Metropolitan Areas: Toronto, Montréal, Ottawa-Gatineau, Québec City, Trois-Rivières, and Peterborough. The survey did not sample the rural and small-town communities between these metropolitan areas — including the communities on the Ottawa–Montreal first segment where ALTO has now estimated 500 farms will be acquired. The 89 per cent benefits perception is a metropolitan-area finding; it does not speak for the people whose land would be taken.

    The same study records that even among its metropolitan-area respondents, around 30 per cent were moderately or extremely concerned about land acquisition and impacts on natural habitats. That concern figure, in turn, is generated from a sample that excludes the populations most directly exposed to those impacts.

    The combined picture

    The 500 farms on the Ottawa–Montreal first segment face a statutory regime that strips standard procedural protections, and an academic public-opinion record that was built without consulting them. The agricultural associations’ demands documented in the sections that follow — for independent impact assessment, binding crossing specifications, broader land-classification scope, and a project pause — are made in this context. They are demands made on behalf of communities that have been legislatively expedited and empirically unrepresented.

    ALTO’s Published Framework

    What ALTO has now committed to in writing

    ALTO has published, in two pages, the framework it intends to use for engagement with affected agricultural property owners. The Property Acquisition Process page sets out a four-step process applying to all property acquisitions: identification of required properties, direct communication with property owners, negotiations, and completion of the transaction. The Agricultural Land page sets out the elements specific to working with the agricultural community.

    Compensation: independent professional appraisals at the time of negotiation, with appraisal values explicitly excluding any reduction or appreciation in value caused by the project itself or by prior announcement of the project; market value plus agricultural and business losses; relocation costs where required; reasonable third-party costs covered by ALTO, including independent appraisal and legal fees.

    Infrastructure: pre-construction inspection of existing tile drainage systems with documentation of pre-construction conditions, repair or replacement of damage caused during construction, restoration of drainage function to pre-construction conditions, and replacement infrastructure at ALTO’s cost where changes are required. Topsoil to be stripped, stored, and replaced separately from subsoil. Three-metre security fencing along the future tracks, both temporary during construction and permanent before construction completion.

    Crossings: grade-separated overpasses and underpasses for people, vehicles, animals, and equipment, plus a parallel access road shareable with farmers; the long-term maintenance approach for grade-separated crossing structures is, in ALTO’s own published words, still being developed.

    Governance: an agricultural land trust under consideration as one approach to community benefits; collaboration agreements with associations under exploration.

    These commitments represent a meaningful procedural advance for ALTO. Before the consultation closed, the project had no written, public-facing acquisition framework. Owners and stakeholders had no document to point to. The framework now exists. The question this brief examines is whether the framework, as published, addresses what the major farm associations have publicly asked for.

    Comparison · Ontario & Quebec

    Ontario Federation of Agriculture & Union des producteurs agricoles

    On February 27, 2026, the Ontario Federation of Agriculture and l’Union des producteurs agricoles issued a joint press release calling for an immediate suspension of the ALTO project. The release identified five operational demands directed to provincial and federal governments and to ALTO. Together they represent the agricultural producer community of the corridor’s two provinces. OFA/UPA

    The Association’s DemandALTO’s Published Commitment
    1. Stay out of prime agricultural areas. OFA describes Ontario’s farmland as a strategic provincial and national asset whose highest and best use is agriculture; the agriculture and agri-food sector contributes $51 billion annually to the Ontario economy and employs about ten per cent of the provincial work force. The proposed alignment is currently planned through some of the most productive farmland in Ontario and Quebec.ALTO’s published framework contains no commitment to stay out of prime agricultural areas. The May 2 estimate of approximately 500 farm properties on the Ottawa–Montreal first segment alone confirms that the alignment crosses substantial agricultural land. The framework references following existing property limits where possible, but this is a goal rather than a binding commitment, and the engineering constraints (60-metre right-of-way, 320 km/h alignment geometry, 7-km straightening recovery) limit how much this goal can be honoured in practice.
    Status:Not met
    2. Avoid breaking farms into smaller pieces; keep fields and farm operations whole. Severance — the bisection of a farm by the rail corridor with parts of the operation on each side — creates operational, drainage, access, and biosecurity problems that compound over the life of the farm.Aspirational language only. ALTO’s chief executive has stated publicly that ALTO will try to follow the existing limits of properties. There is no binding commitment to keep farm operations whole, no guarantee that severance will be avoided, and no compensation mechanism specific to severance impacts beyond the general agricultural-loss provision. The 60-metre fenced corridor with three-metre walls and no level crossings makes whole-farm preservation extremely difficult to deliver wherever the alignment crosses contiguous farm parcels.
    Status:Not meaningfully met
    3. Protect farm drainage systems essential for crop production. Tile drainage represents a significant long-term investment for farms; disruption affects both immediate productivity and long-term land value.Substantively addressed in the published framework. ALTO commits to pre-construction inspection of existing drainage systems with documentation of pre-construction conditions, repair of any damage caused during construction, restoration of drainage function to pre-construction conditions, and installation of replacement infrastructure at ALTO’s cost where changes are required. Temporary measures or compensation may apply during construction if drainage is affected. This is the closest match between an OFA / UPA demand and an ALTO commitment in the published framework. Enforcement during construction remains the operational test.
    Status:Substantively addressed
    4. Address farmers’ concerns about construction impacts and ongoing costs. Includes fencing, and the building, upgrading, and long-term maintenance of safe farm crossings for equipment and livestock.Partially addressed; the binding-specification demands are not met. On fencing: ALTO commits to install and maintain three-metre security fencing along the future tracks; temporary fencing during construction; permanent fencing before construction completion. On crossings: ALTO references grade-separated overpasses and underpasses, plus a parallel access road shareable with farmers. ALTO has not committed to crossing spacing standards, minimum dimensions, or any binding-specification requirement on crossings. The long-term maintenance approach for grade-separated crossing structures is, in ALTO’s own published words, still being developed.
    Status:Partially addressed
    5. Ensure agricultural impact assessments are independent, thorough, and publicly available. Without independent assessment, the operational implications of the corridor for agricultural production cannot be evaluated by farmers, by regulators, or by the public.No commitment in the published framework. ALTO’s published sequence is route first (corridor narrowed in autumn 2026), then letters to identified owners, then negotiations. There is no commitment to commission, complete, or publish independent agricultural impact assessments before the corridor is narrowed. The federal Impact Assessment Act process will provide one set of environmental and social assessments, but agricultural-specific independent impact assessment is not committed in the framework.
    Status:Not met
    Comparison · National Federation

    Canadian Federation of Agriculture

    On February 25, 2026, the Canadian Federation of Agriculture passed a resolution at its Annual General Meeting urging the federal government to immediately halt the ALTO project to allow for a thorough economic, social, and environmental impact assessment and meaningful consultation with affected agricultural, forestry, and rural communities. The resolution was put forward by UPA President General Martin Caron and seconded by OFA President Drew Spoelstra. CFA represents the federated provincial federations across Canada. CFA via OFA/UPA

    The Association’s DemandALTO’s Published Commitment
    1. Halt the project to allow for a thorough economic, social, and environmental impact assessment and meaningful consultation. The resolution conditions any subsequent agricultural protections on the prior assessment of whether the project itself should proceed in the proposed form.Not met. The project is proceeding to corridor narrowing in autumn 2026, with land acquisition on the Ottawa–Montreal segment to begin in late 2026 or early 2027. The published $60–90 billion cost figure has been characterized by ALTO’s chief executive (May 2 interview) as a working assumption rather than a cost estimate, with reliable cost estimates expected only in 2027 or 2028 after detailed engineering follows alignment selection. The project is not being halted for that work to be completed before route selection.
    Status:Not met
    2. If the project ultimately proceeds, properly sized agricultural and forestry crossings of minimum 10 metres. The 10-metre figure is specified in the resolution as the minimum that allows modern agricultural equipment, livestock, and forestry vehicles to cross safely with appropriate clearances.Not met as a binding specification. ALTO’s published framework references grade-separated overpasses and underpasses for people, vehicles, animals, and equipment, but does not commit to a minimum crossing dimension. The 10-metre minimum from the CFA resolution is not present in the framework. The long-term maintenance approach for grade-separated crossing structures is, in ALTO’s own words, still being developed.
    Status:Not met
    3. Fair, proportional compensation reflecting the permanent and more significant impact of the rail corridor compared to highways or transmission lines. The recognition that HSR’s impact is permanent and more significant than other linear infrastructure is the analytical foundation for the proportionality demand. The corridor will be fenced on both sides with three-metre walls, with no level crossings, in perpetuity.Partially addressed; the comparative recognition is absent. ALTO commits to compensation including market value, agricultural losses, business losses, relocation costs, and third-party costs. The recognition that HSR’s permanent impact is more significant than highways or transmission lines is not present in the framework. ALTO’s chief executive has compared the project to historical highway construction (May 2 interview), explicitly invoking the framing the CFA resolution rejects.
    Status:Partially addressed
    Comparison · Beef Sector

    Beef Farmers of Ontario

    On March 3, 2026, the Beef Farmers of Ontario formally endorsed the OFA / UPA position and called on the federal government and the Minister of Transport to immediately halt the ALTO project. BFO members voted strongly in favour of a resolution at the BFO Annual General Meeting on February 19, 2026. The BFO statement adopts the OFA / UPA five-point demand list and adds one specific BFO requirement. BFO

    The Association’s DemandALTO’s Published Commitment
    BFO’s additional demand: Protect all actively farmed lands, not only prime agricultural classifications. BFO writes that no lands currently in agricultural production should be impacted by the project — including marginal lands essential to livestock and forage production — unless comprehensive mitigation strategies, properly designed agricultural accommodations, and compensation that fully reflects both immediate and long-term operational impacts are secured in advance. Beef operations require contiguous land bases including pasture, hay ground, and grazing lands. Marginal lands by official classification often play essential operational roles in livestock and forage production.Not addressed. ALTO’s published framework does not differentiate between land classifications when describing acquisition. The 500-farm figure represents total agricultural property acquisitions, not categorized by classification. There is no commitment to broaden protection beyond prime agricultural land, no mechanism to recognize marginal-classification lands as operationally essential to livestock or forage production, and no guarantee that compensation will reflect the operational role of such lands rather than their tax or zoning classification.
    Status:Not met

    BFO’s additional demand sharpens the OFA / UPA list by requiring that protections apply to all actively farmed lands — pasture, hay ground, and grazing lands — and not only to lands meeting the formal prime agricultural classification standards. For livestock-based operations in particular, this distinction is operational rather than rhetorical: marginal-classification lands often carry the forage and pasture function that makes the rest of the operation viable. The framework’s silence on this distinction means that BFO members cannot evaluate whether their operations would be protected by the published commitments.

    Comparison · Structural Critique

    National Farmers Union

    The National Farmers Union has issued multiple statements on the ALTO project, including a national media release titled “Alto High Speed Rail: The Wrong Project, in the Wrong Way, at the Wrong Time” and an NFU-Ontario policy position dated March 2026. NFU’s position differs from those of OFA, UPA, CFA, and BFO in being structural rather than property-level. NFU vice-president of policy Phil Mount has additionally been quoted in The Globe and Mail (May 1, 2026) characterizing ALTO’s compensation framework as empty reassurances aimed at urban constituents seeking assurance that affected farmers will be treated right. NFU

    NFU’s ConcernALTO’s Published Commitment
    1. Transparency of the project’s underlying business case. NFU writes that ALTO has wrapped up its consultation process without releasing a feasibility study or business plan, and characterizes ALTO’s 2025 Explanatory Document as a marketing brochure rather than a substantive document. NFU notes that fully costed plans for HSR projects in 1995 and 2011 were rejected by parliamentarians once the numbers were published.The published framework does not address this concern, and the May 2 disclosure compounds it. ALTO has not released a feasibility study or business plan. ALTO’s chief executive has now publicly characterized the published $60–90 billion cost figure as a working assumption rather than a cost estimate, with reliable cost estimates to follow detailed engineering in 2027 or 2028 — after the corridor is selected. The federal benefit claims that depend on a cost figure (notably $35 billion in GDP impact and 51,000 construction jobs) inherit the working-assumption status.
    Status:Not addressed
    2. The public-private-partnership delivery model. NFU characterizes the partnership between ALTO (a Crown corporation) and Cadence (a multinational consortium including AtkinsRéalis, formerly SNC-Lavalin) as a delivery structure that severely limits public oversight and that, in the event of cost overruns, places taxpayers as the only party held accountable. NFU contrasts this with discrete private contracts for specific pieces of work with clearly-defined timelines and budgets.Not addressed. The acquisition framework does not speak to the project’s overall delivery model. Whether the framework itself can be enforced as committed depends on contractual mechanisms and oversight structures that are outside the scope of the framework’s published text.
    Status:Not addressed
    3. The absence of complementary public transportation infrastructure. NFU argues that successful HSR networks in other jurisdictions rely on a strong foundation of pre-existing complementary public transportation. Canada lacks that foundation: VIA ridership at approximately four million annually compared with the 1920s peak of fifty-one million; commuter mode share dominated by private vehicles in Toronto, Montreal, and Ottawa; underdeveloped urban transit at the corridor’s endpoints.Not addressable through the acquisition framework. The published framework concerns property acquisition and engagement with agricultural producers. It does not speak to the broader transit-policy questions NFU raises. These are project-level rather than acquisition-level questions, and the framework neither answers nor purports to answer them.
    Status:Not addressed

    NFU’s structural objections occupy a different analytical register from the OFA / UPA / CFA / BFO operational demands. NFU does not say that ALTO’s compensation should be higher or that crossings should be wider; it says that the project as currently scoped should not proceed. ALTO’s published acquisition framework is therefore not the right document against which to measure the NFU position. The NFU position is, in its own terms, a position on the project itself — one that the May 2 working-assumption disclosure substantially reinforces.

    Cross-Cutting Findings

    Five patterns across the operational demands

    Across the four associations whose demands are operational rather than structural — OFA, UPA, CFA, and BFO — five patterns emerge.

    One area of substantive alignment

    Tile drainage is the only demand on which ALTO’s published framework substantively meets what the associations have asked for. Pre-construction inspection, repair-or-replace during construction, restoration to pre-construction conditions, and replacement infrastructure at ALTO’s cost where changes are required — these commitments respond directly and operationally to the OFA / UPA / CFA / BFO concern that drainage protection be guaranteed. The remaining test is enforcement during construction, but the published commitment is real.

    The binding-specification gap

    On the questions where the associations have asked for binding specifications — minimum 10-metre crossings (CFA), spacing standards, defined long-term maintenance commitments — ALTO’s published framework speaks in qualitative terms (“grade-separated overpasses and underpasses”, “parallel access road shareable with farmers”) without quantification. Imbleau’s May 2 acknowledgement that the long-term maintenance approach for grade-separated crossing structures is still being developed confirms the gap. Specifications that have not been committed at the framework stage will be very difficult to introduce after corridor selection, given the engineering constraint that alignment cannot be meaningfully moved at fine scales after that decision.

    The independent-assessment absence

    OFA and UPA’s fifth demand — that agricultural impact assessments be independent, thorough, and publicly available — is shared by CFA’s halt-for-assessment resolution and by BFO’s endorsement. ALTO’s framework contains no commitment on independent agricultural impact assessment. The federal Impact Assessment Act process will produce environmental assessments, but agricultural-specific independent assessment with the methodology, scope, and timeline the associations have asked for is not committed. The route-first sequence forecloses the possibility of an independent assessment informing corridor selection.

    The highway-comparison framing

    The CFA resolution’s compensation language calls for fair, proportional compensation reflecting the permanent and more significant impact of the rail corridor compared to highways or transmission lines. ALTO’s chief executive has, on the public record, invoked exactly the comparison the resolution rejects: the framing that the project must proceed in the same way large highways have been built in the past (May 2 interview). The comparison is not merely rhetorical: a fenced 60-metre right-of-way with three-metre security walls and no level crossings creates a more permanent severance than a highway of comparable width, where level crossings remain possible and where the right-of-way edge is not fenced as an absolute barrier.

    The pause demand

    OFA and UPA’s joint release calls for an immediate suspension of the project. CFA’s resolution urges the government to immediately halt the project. BFO calls on the federal government and the Minister of Transport to immediately halt the project. The four associations whose operational demands this brief examines are unanimous on the threshold question of whether the project should proceed in its current form ahead of the assessments they have asked for. ALTO’s framework is silent on this question because it is not within ALTO’s authority to answer; the Minister of Transport’s response to date has been to confirm the project’s timeline rather than to address the request for a pause.

    Implications for autumn 2026

    What could still be delivered before corridor narrowing

    ALTO’s chief executive has confirmed the project’s working timeline: corridor narrowing in autumn 2026, formal letters to property owners affected by the narrowed Ottawa–Montreal corridor sent before public disclosure of that corridor, land acquisition beginning in late 2026 or early 2027, construction beginning in 2029. Within that timeline, the items the associations have asked for cluster into two categories.

    Deliverable before corridor narrowing

    Independent agricultural impact assessment Commissioning, completion, and publication of independent agricultural impact assessments before the corridor is narrowed in autumn 2026 is operationally possible if begun immediately. The methodology, scope, and timeline would have to be specified now to allow completion within five months. (OFA / UPA / CFA / BFO)
    Binding crossing specifications Adopting a minimum 10-metre standard, plus a published spacing requirement, as a project commitment that will inform corridor narrowing rather than follow it. This is a single decision rather than a study; it could be made now. (CFA)
    Land-classification scope A commitment that protections apply to all actively farmed lands, not only prime agricultural classifications. This is a definitional decision; it could be made now. (BFO)
    Compensation recognition A published commitment that compensation will reflect the permanent and more significant impact of HSR compared to highways or transmission lines, with the methodology specified. This is a framework-level decision; it could be made now. (CFA)

    Depends on the project-level pause demand

    Pause for thorough assessment The four associations’ shared call for a halt to allow proper assessment is, by its own terms, conditional on the federal government’s willingness to pause the timeline. ALTO’s framework cannot deliver this because it is not within ALTO’s authority. The Minister of Transport’s response to date is the relevant indicator: as of May 2026, the project is proceeding on the published timeline.
    NFU’s three structural concerns Transparency of the business case; the public-private-partnership delivery model; the absence of complementary public transportation infrastructure. These are concerns about the project itself, and the May 2 working-assumption disclosure substantially reinforces the first of them. Whether they are addressed depends on decisions at the federal cabinet level, not at the level of ALTO’s published commitments.
    Where things stand · May 2026

    Summary ledger

    In summary, against the public demands of the major Canadian farm associations:

    Substantive
    Tile drainage protection (OFA / UPA / CFA / BFO): substantively addressed in ALTO’s published framework. Enforcement during construction remains the operational test.
    Substantive
    Independent appraisals at appraisal-date neutrality (overlaps with the spirit of the OFA / UPA / CFA / BFO compensation demands): substantively addressed.
    Substantive
    ALTO covers owners’ independent appraisal and legal costs (overlaps with the spirit of the compensation demands): substantively addressed.
    Partial
    Crossings — qualitative reference to grade-separated overpasses and underpasses (OFA / UPA item 4; CFA item 2): partially addressed; no minimum dimensions, no spacing standard, long-term maintenance approach still being developed.
    Partial
    Compensation — market value plus losses (CFA item 3): partially addressed; the recognition that HSR’s permanent impact is more significant than highways or transmission lines is absent.
    Not met
    Stay out of prime agricultural areas (OFA / UPA item 1).
    Not met
    Avoid breaking farms into smaller pieces; keep operations whole (OFA / UPA item 2): not meaningfully met.
    Not met
    Independent agricultural impact assessment, public, before route selection (OFA / UPA item 5).
    Not met
    Halt for thorough assessment (CFA item 1; OFA / UPA pause demand; BFO endorsement).
    Not met
    Minimum 10-metre agricultural crossings (CFA item 2): not met as a binding specification.
    Not met
    Protection of all actively farmed lands, not only prime agricultural classifications (BFO additional demand).
    Not met
    NFU structural concerns: not addressed by an acquisition framework, and substantially reinforced by ALTO’s May 2 working-assumption disclosure.

    ALTO’s chief executive has put the operational scale of the agricultural impact on the Ottawa–Montreal first segment at approximately 500 farms; comparable figures for the remainder of the corridor have not been disclosed. The public demands of the associations representing the farmers on those 500 farms — and on the farms across the rest of the corridor still to be quantified — are not, in the main, met by the framework ALTO has published. The associations are not asking for revisions to a framework whose existence they accept; they are, with the partial exception of NFU’s structural framing, asking for assessments that have not been done and protections that have not been committed.

    Download Full Brief
    Five Hundred Farms (PDF, 14 pages)
    Complete demand-by-demand analysis for federal decision-makers, farm associations, MPs, and constituents tracking the agricultural file
    Download PDF
    Sources

    Primary documents and statements

    1.
    Ontario Federation of Agriculture and l’Union des producteurs agricoles, joint press release, February 27, 2026. ofa.on.ca
    2.
    Canadian Federation of Agriculture, Annual General Meeting Resolution on the ALTO project, February 25, 2026.
    3.
    Beef Farmers of Ontario, statement on the ALTO High-Speed Rail project, March 3, 2026. ontariobeef.com
    4.
    National Farmers Union, “Alto High Speed Rail: The Wrong Project, in the Wrong Way, at the Wrong Time,” NFU media release; NFU-Ontario policy position, March 2026. nfu.ca
    5.
    ALTO, Property Acquisition Process page, published April 2026. altotrain.ca
    6.
    ALTO, Agricultural Land approach page, published February 17, 2026, updated April 2026. altotrain.ca/agricultural-land
    7.
    Andrew Pinsent, “High-Speed Rail in Eastern Ontario: Rural Backlash, Land Expropriation and Next Steps,” CFRA / Substack, May 2, 2026. Substack
    8.
    Mathieu Berger, “Montreal–Ottawa high-speed rail line could cross 1,700 properties, Alto predicts,” CBC News / Radio-Canada, May 5, 2026 — clarifies that the 1,700-property / 500-farm estimate applies specifically to the Ottawa–Montreal first segment. CBC News
    9.
    Bill Curry, “Ottawa train station isn’t ideal location for high-speed rail terminal, Transport Minister says,” The Globe and Mail, May 1, 2026 — carries the Phil Mount / NFU response to ALTO’s compensation framework. Globe and Mail
    10.
    Priscilla Ki Sun Hwang, “How Alto plans to buy out property owners for its high-speed rail plans,” CBC News, May 1, 2026. CBC News
    11.
    Budget Implementation Act, 2025, No. 1 (Bill C-15), Statutes of Canada 2026, c. 3. Royal assent March 26, 2026. The High-Speed Rail Network Act is enacted as Division 1 of Part 5; expropriation provisions discussed in this brief appear at sections 17, 18, 21 and 23 of that Act. parl.ca
    12.
    Standing Senate Committee on Transport and Communications, Second Report (subject-matter study of Divisions 1, 2, 24, 28 and 29 of Part 5 of Bill C-15), February 12, 2026. sencanada.ca
    13.
    Zhang, B., Negm, H., & El-Geneidy, A. (2025). High-Speed Rail in Canada: Insights from a corridorwide survey and a financial analysis. Transportation Research at McGill, McGill University.