Tag: P3

  • Estimated not simulated

    Estimated, Not Simulated

    The journey times behind ALTO were drawn from a spreadsheet of international averages — not from a model of the actual corridor. What that distinction means, and who set the target.

    Critical Finding

    A government record released under the Access to Information Act shows that, of the journey times prepared for the project, only the slowest case was produced by an actual simulation of the railway. That case was a 110 mph (177 km/h) train — a roughly four-hour Toronto–Montréal trip. Every faster time, including those near the speeds ALTO now markets, came from a spreadsheet that applied average speeds borrowed from intercity railways in other countries.

    The technical memorandum describes those faster figures, in its own words, as “for information and comparison purposes.” And the email chain attached to it records the most senior Transport Canada official on the file directing that the times not assume Toronto speeds above 160 mph (257 km/h), because a higher figure was “not the intent of the Government.” The journey time, in other words, was managed as a policy and cost target — not derived as an engineering result.

    The Record

    What the document is

    The release (A-2025-00333) was obtained under the Access to Information Act and provided to the Initiative. It consists of an email chain dated August 30 to September 4, 2023 among Transport Canada and Via HFR / Via TGF officials and their technical advisers, together with the attached memorandum “VIA HFR-TGF Journey Times.” It dates from the procurement period, when the project was still a high-frequency rail (HFR) programme under Transport Canada’s lead, before the February 2025 announcement re-scoped it as high-speed rail at 300 km/h.

    The memorandum is the engineering note that sits beneath the project’s headline travel times. It is explicit about how those times were calculated — and it used two very different methods for two different parts of the answer.

    The Distinction That Matters

    Two ways to get a journey time

    A train’s journey time is the single number a project like this is sold on — “Toronto to Montréal in X hours.” There are two fundamentally different ways to produce that number, and they are not equally reliable.

    A simulation builds a digital twin of the real railway and “drives” a train along it. The software knows the actual track: every curve that forces the train to slow, every hill, every station stop, where the signals are, how fast the specific train accelerates and brakes, and whether other trains — including freight — are in the way. It runs the trip second by second on that line and reports how long it genuinely takes. The memorandum names the tool used for this: RailSys, drawing on the JPO’s 2021 Rail Operational Summary Report. It is the railway equivalent of a flight simulator, or of a mapping app with live traffic.

    A spreadsheet estimate does something far cruder: it takes the distance, assumes an average speed borrowed from how fast trains run in other countries, and divides one by the other. It never looks at this corridor’s actual geometry, terrain, urban approaches, or shared freight track. The memorandum is candid that its faster figures are of this kind — an “estimated calculation based on the maximum permissible speed,” provided “for information and comparison purposes.”

    Simulation — the RailSys toolSpreadsheet estimate
    Drives the actual route. Models every curve, gradient, station stop, signal and conflicting train on the real Toronto–Québec line, second by second. Distance ÷ an assumed average speed. Takes the route length and an average operating speed benchmarked to comparable intercity rail abroad, and divides.
    Knows the corridor. A curve too tight for high speed shows up as a slower section; a freight train ahead shows up as lost minutes. Constraints surface before construction, not after. Blind to the corridor. Cannot see this line’s curves, hills, city approaches or freight sharing. The memorandum labels its outputs indicative only.
    What ALTO simulated. Only the 110 mph (177 km/h) base case — roughly a four-hour Toronto–Montréal trip. What ALTO estimated. Every faster time, including the 160 and 186 mph figures (257 and 300 km/h) closest to the marketed speeds.

    The difference is the difference between “we modelled it and it works” and “we estimated it from comparables.” The first is a tested result for this railway. The second is an educated guess that a later, detailed study would have to confirm.

    What Was Actually Run

    The only simulated number is the slow one

    ~4 hrs
    the only Toronto–Montréal time actually simulated (110 mph / 177 km/h base case)
    RailSys, per the memorandum
    Spreadsheet
    the source of every faster journey time on the page
    benchmarked to foreign averages
    160 mph
    (257 km/h) — the speed ceiling set as “the intent of the Government”
    TC official, Aug–Sept 2023

    The memorandum’s own tables make the gap plain. The single time it produced by simulation — the 110 mph (177 km/h) base case — is roughly 3:59 to 4:19 for Toronto–Montréal. The faster times on the same page, for a 186 mph (300 km/h) or 160 mph (257 km/h) train, run from about 2:40 to 3:10. But those faster figures are the spreadsheet ones. The four-hour trip is the only number anyone actually drove through the model. The under-three-hour trips that make high-speed rail attractive were never simulated for this corridor.

    This matters because the public ALTO project is now built on 300 km/h (186 mph) running. Even the “calculated” 186 mph (300 km/h) times in this 2023 record trace back to the spreadsheet, not the simulator — and the simulator was only ever pointed at the slow case.

    A second problem: not the door-to-door time

    There is a second issue with these numbers, separate from how they were produced. Every figure here — simulated or estimated — is a train-in-motion time, measured platform to platform. It is not the door-to-door time that decides whether a traveller picks rail over flying, and door-to-door time depends on something ALTO has not settled: where the stations are. With downtown stations at both ends the corridor is competitive; with the suburban or peri-urban stations most consistent with the project’s cost structure, the advantage over air narrows or disappears. A separate academic submission to the consultation went further, noting that ALTO’s published times do not appear to even include the time for a stop in Ottawa — so the in-motion figures may be understated before the door-to-door question is reached. We treat that in full in The Station Location Problem and The Last Mile; the point here is narrower — the headline time is an estimate, and even taken at face value it is not the number that matters.

    Who Set the Target

    The journey time as a government decision

    The instruction to hold the journey times down did not come from a technician. The email chain records that when a Toronto figure was put forward assuming sustained speeds above 160 mph (257 km/h), a Transport Canada official objected that it “assumes a full journey time from Toronto at speed greater than 160, which is not the intent of the Government,” and explained that the intent was to have bidders identify the segments with the lowest marginal cost for higher speed. The exchange closes on September 4, 2023 with the project director’s note: “No change to journey time agreed by Vincent.”

    That official is Vincent Robitaille. According to Transport Canada’s own published biography, Robitaille has served as Assistant Deputy Minister – High Frequency Rail since December 2021 — the month the project’s governance passed to a Transport Canada–led integrated team — and he leads that team. His background before the role was in commercial policy and financing, not rail engineering: from 2018 to 2021 he was Director General of Transport Canada’s Centre of Excellence on Strategic Investments, working on the commercial elements and alternative financing of major transportation investments, and before that he led the public-private-partnership procurement of the new Champlain Bridge Corridor in Montréal. His credentials are financial and project-management designations (CFA, PMP, Certified Director, and an MBA). Transport Canada

    Why the background is relevant, not incidental

    This is an observation of record, not of motive. The person defining the journey-time ceiling as the Government’s intent — and steering bidders toward “the lowest marginal cost” rather than the fastest trip — is the project’s most senior Transport Canada official, whose professional expertise is procurement and project financing. It is consistent with a journey time being treated as a commercial and cost target to be managed, rather than an engineering output to be measured. The released record shows the target being set; it does not require any inference about why.

    Two Years Later

    The same official, now selling the fast times

    In a public podcast interview in December 2025, Robitaille — by then leading the project for Transport Canada — described the corridor to a general audience in precisely the terms the 2023 record could not support with simulation: Montréal reachable in well under current rail times, a city you could reach for a day trip and return the same evening, trains “every half an hour,” the corridor as “commuting distance.” Those are the fast, frequent-service figures — the ones drawn from the spreadsheet.

    The internal record from 2023 shows the same official holding the specification below those speeds — directing that journey times not assume sustained running above 160 mph (257 km/h), because faster was “not the intent of the Government” — and relying on benchmarked estimates for anything quicker. The public pitch and the internal caution are two years apart and point in opposite directions. The travel times now used to sell the project are of the kind the same official described internally, in 2023, as indicative.

    The Bottom Line

    A promise, or an estimate?

    When a government tells the public “this train will get you there in X hours,” people reasonably assume engineers modelled the actual route and confirmed it. This record shows that, for the fast times, they did not. They did the back-of-an-envelope version — distance against speeds observed in other countries — and said so internally. A spreadsheet estimate is a hope; a simulation is the closest thing to a tested promise. The faster ALTO travels in its marketing, the further it gets from the only journey time anyone actually ran.

    One caveat, stated plainly so the point is not overdrawn. The memorandum does say these estimates were always meant to be refined through later design and operational modelling by the eventual private partner. So the fair claim is not that the numbers were invented. It is that the detailed validation was deferred, and that as of this 2023 record the project’s faster journey times — including those near what is marketed today — had no corridor-specific engineering behind them, only benchmarked estimates. No simulation of high-speed running on the Toronto–Québec line appears anywhere in the released record.

    Sources

    Primary documents

    1.
    Transport Canada / Via HFR (Via TGF), “VIA HFR-TGF Journey Times” (HFR JT note 20230831) and accompanying email chain, August 30 – September 4, 2023. Released under the Access to Information Act as file A-2025-00333.
    2.
    Joint Project Office, Phase 2C Rail Operational Summary Report (2021) — the RailSys simulation source referenced in the memorandum for the 110 mph (177 km/h) base case.
    3.
    Transport Canada, Briefing Documents 2025, biography: “Vincent Robitaille — Assistant Deputy Minister – High Frequency Rail.” tc.canada.ca
    4.
    “From Bridges to Trains: Career lessons with Vincent Robitaille,” The Supply Chain Ambassador podcast, premiered December 3, 2025. Public interview; transcript auto-generated. youtube.com
  • Modal shift subsidy

    Citizen Research Initiative · Modal Shift Analysis · Note 4

    The Subsidy Frontier and the ALTO Operating Trilemma

    High ridership and low subsidy are mutually exclusive on this corridor. A continuous-spectrum framework relating subsidy, fare revenue, ridership and net public cost — and the structural reason the published 24-million target sits outside every operating point on the frontier.

    ⚠ What This Note Examines

    This note extends Notes 1, 2 and 3 from three discrete regimes to a continuous subsidy spectrum, relating four quantities along it: annual operating subsidy, ridership, fare revenue, and net public cost. It identifies the welfare-efficient and revenue-maximising operating points, and adds full-cost accounting across three capital-cost scenarios.

    The result is the corridor’s operating trilemma: high ridership, low subsidy, and P3 break-even cannot be achieved simultaneously. The choice among them is a single-degree-of-freedom political-economy decision — one that the published business case does not make explicit.

    Bottom Line

    The modal-shift framework from Notes 1 and 2, combined with the demographics of Note 3, produces a fixed frontier of (subsidy, ridership) combinations. The corridor cannot simultaneously deliver Regime A ridership (11–12 million) at Regime C subsidy levels ($0.5–1.5 billion/yr). Any public communication implying otherwise is selecting figures from different points on the frontier and presenting them as one outcome.

    Ridership rises concavely with subsidy — from ~5M at $0.3B/yr to ~12M at $5B, hitting diminishing returns as it approaches the modal-shift ceiling. Revenue is hump-shaped, peaking at ~$1.29 billion at $1.9 billion subsidy. The marginal net public cost per added rider has a U-shaped minimum at ~$400/rider near Regime B. Different objectives select different optima: maximising revenue or minimising per-rider cost → Regime B; minimising total public cost → Regime C; maximising ridership under a fiscal cap → Regime A.

    And the P3 break-even corner is structurally unreachable: against an achievable peak fare revenue of $1.29 billion, P3 break-even revenue is ~$4.3 to $5.0 billion — a gap of $3.17 billion/yr at peak revenue, even under the proponent’s own $75B capex base case. ALTO’s published 24-million-by-2055 target sits outside every point on the frontier and is incompatible with any defensible operating-regime choice.

    Download
    Modal Shift Note 4 — Subsidy Frontier & Optimisation (PDF)
    The full note with all four figures and two tables: the trilemma, the ternary locus, the four-panel frontier, the scissors chart, the five optimisation objectives, and the full-cost accounting across three capital scenarios
    Download PDF
    The Trilemma

    No operating regime achieves all three objectives

    The corridor faces three ideal objectives that cannot be reconciled: high ridership (at the level of ALTO’s public targets), low subsidy (operating surplus), and P3 break-even (revenue covering operating cost plus private capital service). Every point inside the realistic operating frontier is achievable under some combination of fare, subsidy and modal-shift parameters; every point outside it is structurally infeasible.

    The ALTO operating trilemma: a dashed outer triangle of three ideal objectives with a smaller solid feasible operating region inside, and Regimes A, B, C positioned within it
    Figure 1. The ALTO operating trilemma. The dashed outer triangle marks the three ideal corners; the solid inner triangle is the realistic operating frontier. Regimes A and C approach their respective corners but cannot reach them; Regime B sits on the frontier edge, achieving the revenue peak. The P3 break-even corner is structurally unreachable: operating cost (~$1.8–2.5B/yr) plus private capital service ($2.49B/yr at the $75B base case) puts break-even revenue at ~$4.3–5.0B/yr, against an achievable peak of $1.29B at Regime B — a $3.17B/yr gap that operating-posture choice alone cannot close.
    The operating locus in objective space, ternary view: a one-dimensional curve tracking the low-subsidy to high-ridership edge, never entering the P3 break-even corner
    Figure 2. The operating locus in objective space, ternary view. Each operating point is mapped to barycentric coordinates of its normalised achievement of the three objectives. Two features stand out: the locus is a one-dimensional curve, not a region — the corridor has only one operational degree of freedom (the subsidy level); and it tracks the low-subsidy ↔ high-ridership edge closely, never entering the P3 break-even wedge. The maximum P3 score along the locus is ~0.30 under the $75B base case. The trilemma is not three symmetric tradeoffs but a single dominant tradeoff (ridership ↔ subsidy) with P3 break-even as a structurally unreachable third axis.
    1 · Framework

    From three regimes to a continuous spectrum

    Note 3 developed three discrete regimes — A (heavy subsidy), B (moderate, at parity with air), C (minimal, P3 yield management) — producing aggregate corridor modal shares of ~40, 30 and 22% and requiring annual operating subsidies of ~$3.5B, $2.0B and $1.0B. This note extends that to a continuous subsidy spectrum to identify the optimisation properties of the corridor’s operating posture.

    The framework relates four quantities along the spectrum: annual subsidy (the federal operating contribution for the chosen fare posture), ridership (the resulting modal shift across air, road and existing rail), fare revenue (riders × average fare), and net public cost (subsidy minus revenue, negative meaning self-financing). Each is anchored on Note 3’s central demographic 2055 scenario (corridor population 20.1 million, addressable trips 34.2 million). The mapping from subsidy to fare ratio is a smooth logistic reproducing the three regime anchors — ~1.3 at $1.0B (deep premium), ~1.0 at $2.0B (parity), ~0.6 at $3.5B (deep discount) — and the mapping from fare ratio to per-mode capture comes directly from the Note 1 and Note 2 S-curves.

    2 · The Frontier

    Ridership, revenue, and net public cost vs subsidy

    Disaggregating the relationships folded together in Note 3’s regime summary reveals the corridor’s subsidy frontier across the continuous spectrum, with the three regime anchors (C, B, A) marked.

    Four-panel subsidy frontier: ridership vs subsidy, revenue vs subsidy, net public cost vs subsidy, and marginal cost per added rider
    Figure 3. The subsidy frontier at the central 2055 anchor. (a) Ridership rises concavely from ~5M at $0.3B to ~12M at $5B — diminishing returns toward the modal-shift ceiling. (b) Fare revenue peaks near $1.9B subsidy at ~$1.29B, then declines as fare cuts overwhelm ridership gains — a Laffer-like structure. (c) Net public cost crosses zero near $1.3B subsidy: below it the corridor runs a surplus, above it a net outlay rising to ~$4B at $5B subsidy. (d) Marginal net public cost per added rider has a U-shaped minimum of ~$400/rider near Regime B, rising to ~$1,000 at Regime A. The ~$85/rider reference line is an illustrative federal value-of-time figure.

    Ridership is concave

    The first dollars of subsidy buy many riders (the steep part of the S-curves); the last buy few (the saturating top). Marginal effectiveness falls sixfold — ~2.5M riders per $B at the low end, ~0.4M per $B at the high end.

    Revenue is hump-shaped

    At low subsidy the corridor is in the premium-fare zone where each rider pays more, so revenue rises with ridership; past the $1.29B peak, the fare reduction overwhelms the ridership gain.

    Net cost flips at ~$1.3B

    Net public cost transitions cleanly from negative (revenue exceeds subsidy) to positive at ~$1.3B subsidy — between the Regime C anchor ($1.0B) and Regime B ($2.0B).

    3 · The Scissors

    Revenue and subsidy versus ridership

    Plotting the same data with ridership on the horizontal axis shows how subsidy and revenue diverge as the corridor moves up the ridership scale — and overlays the federal capital service ($2.49B/yr at the $75B base case), so each regime shows three quantities: operating subsidy, fare revenue, and full federal cost.

    Scissors chart: operating subsidy rising convexly with ridership while fare revenue stays flat, with full federal cost and the three regimes marked against a modal-shift ceiling near 12 million
    Figure 4. Subsidy and revenue against ridership, central 2055 anchor. The two curves form a scissors: subsidy (navy) rises convexly while revenue (terracotta) is essentially flat. At Regime C (6.1M riders) the corridor returns a ~$260M operating surplus — full federal cost ~$2.23B with capital service added. At Regime B (8.2M) it needs ~$710M net operating outlay — full federal cost ~$3.20B. At Regime A (11.2M), ~$2.42B net outlay — full federal cost ~$4.91B. Capital service exceeds operating subsidy at every regime, even under the proponent’s base case. The chart caps at the ~12M modal-shift ceiling; beyond it, each added rider requires sharply rising per-rider subsidy.

    The scissors structure has direct policy implications. Below ~6.5 million annual passengers the corridor runs a net public revenue surplus — fare revenue exceeds the subsidy needed. Above that it crosses into net-public-cost territory, rising convexly with the target. By 11 million (near Regime A) the corridor needs ~$2.4 billion annually in net public outlay above its fare revenue. Beyond 11.5 million the curve steepens sharply — pushing toward the 24-million public target would require an entirely different operating regime than any of the three considered here.

    4 · Optimisation

    Five objectives, five different optima

    The frontier supports several distinct optimisation objectives that each select a different operating posture. There is no single “optimal” point without first specifying the criterion.

    Table 1. Optimal operating posture under different objective functions, central 2055 anchor. The five candidate optima span Regime C (minimum total public cost), Regime B (revenue peak, per-rider welfare efficiency), an intermediate position (total welfare under moderate social-value assumptions), and Regime A (maximum ridership). “Total welfare” includes ridership × value-of-time × emissions avoided − net public cost, and is strongly sensitive to the assumed social value per rider.
    ObjectiveOptimal regimeRiders 2055SubsidyRevenueNet public cost
    Maximise fare revenueRegime B (parity)~8M$1.9–2.0B$1.29B (peak)+$0.7B
    Min. net cost per riderRegime B (parity)~8M$1.9–2.0B$1.29B$400 marginal
    Min. total net costRegime C (yield mgmt)~6M$0.5–1.5B$1.26B+$0.2B or surplus
    Max. ridership s.t. capRegime A (heavy)~11M+$3.5B+$1.08B+$2.4B
    Max. total welfareBetween B and A~9M$2.5B$1.2B+$1.3B

    Four observations follow. Revenue-maximisation and per-rider welfare-efficiency converge on Regime B — not coincidentally, since the same marginal-revenue-equals-marginal-cost condition defines both the Laffer peak and the marginal-cost-per-rider minimum. Minimum-total-net-public-cost points to Regime C or below, where the corridor runs a small surplus but carries only 5–6 million riders — approximately the posture implied by the Cadence consortium’s announced commercial structure. Ridership-maximisation under a fiscal cap points to Regime A or beyond — but reaching the 24-million target would require pushing past Regime A into subsidy well above $5B/yr and modal share above the 40% ceiling, not feasible under the modal-shift framework. And total-welfare-maximisation is strongly sensitive to the assumed social value per rider: at the illustrative ~$85/rider federal value the optimum is at or below Regime C; only at a high $400/rider — crediting network effects, large emissions externalities, and agglomeration benefits — does it move between B and A.

    There is no single “optimal” operating posture without specifying the criterion. The corridor decision is not one quantitative question but three sequential ones: whether to build at all, what fare posture to operate under, and how to communicate the chosen posture transparently.
    5 · Full-Cost Accounting

    Capital service dominates the operating choice

    The subsidy frontier above considers operating subsidy only — but capital cost service dominates the corridor’s total fiscal commitment, and the capital cost itself is deeply uncertain. ALTO’s materials cite ~$60–90 billion, prepared without reference-class adjustment. The CRI’s reference-class analysis (Flyvbjerg methodology on the international HSR cost database, with corridor-specific complexity premia) produces three scenario points: $75B as the proponent-stated P50, $143B as the reference-class-adjusted P50 (after the 44.7% average rail-project overrun), and $264B as the P95 worst case — with the proponent’s $75B sitting at roughly the 25th percentile of the distribution.

    Table 2. Full federal cost implications across three capital cost scenarios. Full annual federal cost = federal share of capital debt service + Regime B operating subsidy of $2.0B/yr (the welfare-efficient point). Full cost per rider = full federal cost ÷ 8M annual riders (Regime B central 2055). Debt service at 6% blended cost of capital, 40-year amortisation, 50% federal share.
    Capital cost scenarioTotal capitalAnnual debt serviceFederal share (50%)Full annual federal costFull cost / rider
    ALTO proponent-stated$75B$4.5B$2.3B$4.3B$540
    CRI reference-class central$143B$8.6B$4.3B$6.3B$790
    CRI P95 worst-case$264B$15.8B$7.9B$9.9B$1,240

    Capital dominates operating

    Even at $75B, federal capital service ($2.3B/yr) exceeds Regime B’s operating subsidy ($2.0B). At $143B it’s more than double; at $264B, ~four times. The full-cost optimisation is dominated by the capital assumption, not the operating regime.

    6 to 14× the benefit

    Full cost per rider spans $540–$1,240. Against an illustrative ~$85/rider value-of-time, the corridor is 6 to 14× more expensive than the public benefit. Even generous $200–250/rider social values stay 2–6× below full cost.

    Decide before committing

    Once the capital is sunk, the A/B/C choice is second-order. The first-order question — whether to build at all — turns on which capital scenario materialises, and the realistic expected value sits between $143B and $264B.

    ALTO’s composite engineering complexity score is 73–81 (upper part of the High band, approaching Extreme) — the Frontenac Arch crossing, the Napanee Limestone Plain karst, the Leda clay segment, the St-Lawrence crossing, and a Canadian P3 delivery record that includes Eglinton Crosstown (+280%), the Confederation Line (+57%), and the Ontario Line (+250% scope-adjusted). Under Flyvbjerg reference-class forecasting, a corridor at this complexity cannot be reliably costed from the lower-complexity international comparators the proponent’s estimate appears to draw on. The realistic expected capital cost is between $143B and $264B, producing a benefit-cost ratio materially below 1.0 across the full plausible range.

    6 · Implications

    What this means for the corridor decision

    The subsidy choice is a policy decision, not a technical one

    The same physical infrastructure produces materially different outcomes depending on the operating point. Regime C gives ~6M riders at a small surplus; Regime A gives 11M at $2.4B net public cost. That choice should be made explicit in the public business case rather than implicit in the procurement structure.

    The welfare-efficient point sits near Regime B

    Parity with air, ~$1.9–2.0B operating subsidy, ~8M riders, ~$400/rider marginal net public cost — also the revenue-maximising point. A welfare-maximising government and a revenue-maximising operator would converge on similar fares. The business case does not specify which objective is being applied.

    Third, and most important: the public ridership targets cannot be reached from any operating point on the frontier developed here. The 24-million-by-2055 figure would require modal share above the 40% ceiling under heavy subsidy, plus upper-case demographic growth, plus full-corridor mature operation in 2055 — three conditions the modal-shift literature does not support simultaneously. The frontier brackets the realistic operating space; ALTO’s published targets sit outside it. An independent review should ask which point on the frontier the corridor is actually targeting, and what fiscal commitment and modal-shift assumptions that point implies.

    High ridership, low subsidy, and P3 break-even cannot be achieved at once. The 24-million target is not the welfare-efficient operating point under any reasonable parameter choice — it is achievable, if at all, only under heroic assumptions about every operating, demographic, and modal-shift variable simultaneously.
    Download Full Note
    Modal Shift Note 4 — Subsidy Frontier & Optimisation (PDF)
    Reference document with all four figures, both tables, the five optimisation objectives, the full-cost accounting, and the methodology and parameters
    Download PDF
    Methodology

    Framework and parameters

    The framework anchors on Note 3’s central demographic 2055 scenario (corridor population 20.1 million, addressable trips 34.2 million at 1.7 trips per capita) with the regime-coupled phase-maturity factor (Regime C ≈ 0.80, B ≈ 0.88, A ≈ 0.94, following a smooth logistic asymptoting to ≈ 0.96). The market structure is air 15%, existing rail 10%, road 75% of the addressable pool. The mapping from operating subsidy S ($B) to fare ratio r is a logistic, r(S) = 0.4 + 1.3 / (1 + exp(S − 1.8)), calibrated to the three regime anchors; the mapping from fare ratio to per-mode capture comes from the Note 1 air–rail S-curve at 3.0 h and the Note 2 road–rail S-curve at τ = 0.5. Average air fare $160 one-way; rail revenue = riders × (air fare × r). Net public cost = subsidy − revenue.

    Capital cost scenarios ($75B / $143B / $264B) are derived from Flyvbjerg reference-class forecasting on the international HSR cost database with corridor-specific complexity adjustments (composite engineering complexity score 73–81). Capital service is computed at 6% blended cost of capital (combining federal debt service and private equity return), 40-year amortisation, 50% federal share. The CRI’s full capital cost analysis is documented separately at citizenresearch.ca.

    Sources

    Principal sources

    2.
    ALTO HSR Citizen Research Initiative (2026). Modal shift between rail and car on the ALTO corridor (Note 2).
    3.
    ALTO HSR Citizen Research Initiative (2026). ALTO ridership envelope, 2035–2080 (Note 3) — the population, trip-generation and regime inputs this note’s frontier is built on.
    4.
    Statistics Canada (2026). Population Projections for Canada (2025 to 2075), catalogue 17-20-0003, released 27 January 2026.
    5.
    Transport Canada (2024). Guide to Benefit-Cost Analysis of Transportation Investments — value-of-time and emissions valuation parameters. — and Treasury Board of Canada Secretariat (2007). Canadian Cost-Benefit Analysis Guide: Regulatory Proposals.
    6.
    Flyvbjerg, B., Holm, M.S. & Buhl, S. — reference-class forecasting and the international rail-project cost-overrun database (44.7% average overrun).
    7.
    ALTO HSR Citizen Research Initiative companion material: the Modal Shift & Ridership synthesis brief, which sets this note alongside Notes 1, 2 and 3.